Specifications
4. TRANSPORT & PLACEMENT WHEATHEART - SELF-PROPELLED AUGER KIT
4.2. PLACEMENT PROCEDURE WHEATHEART & COMPETITOR MODELS
42 IM3 R2
4.2. PLACEMENT PROCEDURE
Follow this procedure when placing the machine into its working position:
1. Be sure there is enough clearance from overhead obstructions, power lines,
or other equipment to move the machine into its working position.
2. Position machine in the desired area. For operating instructions, see Section
5.2.
WHEN PLACING UNDER HOPPER BOTTOM BINS:
1. The wheel u-frame can easily pass through the hopper bin vertical legs.
2. The wheel u-frame does not have to travel over an obstruction.
3. Auger intake is centered between the hopper bin vertical legs. This ensures
that the operator has adequate clearance for auger operation.
4. The auger gearbox will not contact the hopper cone when in it’s final position.
WHEN PLACING INTO FLAT BOTTOM BINS:
1. The wheel u-frame won’t contact the side of the bin when auger is in its final
position.
2. The door of the bin is not obstructed.
3. The auger intake will fit through the bin access door.