SDB680 – INSTALLATION GUIDE TNM-I-E-0046
May 15 Page 35 CONFIGURATION TIER III BASE
28.5. When the write operation is completed, the success or failure of the operation for each VAC,
Site or Base will be indicated in the Comms History area.
4.6.4
Enable Bases
29. On the system I/O page, in the System Monitor area, on the navigation tree, carry out the following:
29.1. To enable all the bases on a system, carry out the following:
29.1.1. Right click on the VAC that you wish to enable. Menu options will be displayed.
29.1.2. From the menu options, select ‘Site Options’ > ‘Enable Site(s)’. The sites enable
warning message will be displayed.
29.2. To enable an individual base, carry out the following:
29.2.1. Right click on the Base that you wish to enable. Menu options will be displayed.
29.2.2. From the menu options, select ‘Base Operations’ > ‘Enable Base(s)’. The base enable
warning message will be displayed.
29.3. On the relevant warning message, select ‘Yes’ to continue.
29.4. In the System Monitor area, on the navigation tree, confirm that the status notification that was
alongside the relevant VAC, Site or individual base has now disappeared.
29.5. In the Comms History area, after a short delay, confirm that the relevant ‘Completed Enabling
Base’ message(s) is displayed.