User Manual
Assemble anchor system as follows: Thread nut (#1)
to bottom of threads on anchor bolt (#3) insert
threads of anchor bolt (#3) through hole on anchor
plate (#2) and secure with nut (#1). Repeat this step
for the remaining anchor bolts. See Figure 2.
NOTE: Each leg of anchor bolts should face the
anchor bolt to the right. See Detail A.
ANCHOR SYSTEM INSTALLATION INSTRUCTIONS
NOTE: For best results with less vibration, anchor system
should be independent of court. If pouring concrete for
both at same time, add an expansion joint in between.
1.
Items needed for Anchor Installation (not included)
9 - 80 lb. bags of concrete (2-3 extra recommended)
1 - post hole digger (optional)
1 - 15/16” open end wrench
1 - 15/16” socket and ratchet (optional)
1 - wheel barrow
1 - garden hose
1 - level
1 - tape measure
1 - concrete form (see note before step 3)
NOTE: When digging hole, if you hit rock
and cannot dig through contact a contractor.
NOTE: Minimum of 18” rear clearance is required behind pole.
1
MODEL NO.
B1030
SILVERBACK
ANCHOR KIT
Before digging hole for anchor system, check for
buried power, gas, water, and telecommunication
lines! Failure to do so could result in serious or fatal
injury! Contact your local utility company if unsure.
Figure 1
20” Diameter
16” Diameter
Concrete
Rebar
36”
Court
Court Level
Anchor Plate must be
square to your court so
the backboard will
line up with court.
Court
Top View
(Key #4)
Determine the location of the anchor system. The proper
location is as close to the court without making contact,
as shown in Figure 1. This, however, is a general rule.
If you need to locate the anchor system in a location
other than this, check system's owners manual for
overhang of your system.