Installation guide

Modifications reserved Page 44/82
OPM_SGS_USM_M10_M15_0US_V030.doc Operating Manual SG Series 100 120 - 150 kVA
7.1.3 From Manual Bypass (Q2) to normal function VFI
Initial status:
Load supplied from Manual Bypass.
1. Close Q1 (Pos. I).
Bypass connects to Load.
LED Load on Bypass lights up.
Rectifier starts automatically and LED
in Rectifier symbol and LED Battery
charge light up.
2. Open Q2 (Pos. O).
LED Manual Bypass turns OFF.
3. Connect the Battery to the UPS by closing the Battery Switch or Fuses, in case of
External Battery .
4. Press inverter on ( I ) key.
Soft-start of Inverter, indicated with
blinking LED.
At the end of Soft-start the LED
remains lit.
Automatic transfer from Bypass to
Inverter.
UPS output LED indicates Load on
Inverter.
The LCD must display on the main screen the status “LOAD ON INVERTER”.
END OF PROCEDURE