Installation Instructions
Document No. 129-556
Installation Instructions
September 10, 2014
Information in this publication is based on current specifications. The company reserves the right to make changes in specifications and
models as design improvements are introduced. Other product or company names mentioned herein may be the trademarks of their
respective owners. © 2014 Siemens Industry, Inc.
Siemens Industry, Inc.
Building Technologies Division
1000 Deerfield Parkway
Buffalo Grove, IL 60089-4513
USA
+1-847-215-1000
Your feedback is important to us. If you have
comments about this document, please send them
to SBT_technical.editor.us.sbt@siemens.com
Document No. 129-556
Printed in the USA
Page 2 of 2
3. Reconnect the latch; you will hear it click when it
is properly closed. The conductor should be in
the inside of the CT Window. See Figure 3.
Figure 3. Installed CT.
4. Repeat Steps 1 through 3 if you are using more
than one CT.
5. (Optional) Use two zip ties to secure the CT to
the conductor by wrapping one zip tie around
each of the CT's mounting brackets. This will
ensure that the CT does not slide on the
conductor once installed. See Figure 4.
Figure 4. CT with Zip Ties Installed.
6. Connect the white wire on the CT to the positive
terminal (+) on the measuring device. See
Figure 5.
7. Connect the black wire on the CT to the
negative terminal (-) on the measuring device.
No connection will be made to the shield (S)
terminal.See Figure 5.
8. If the digital energy meter is powered, verify that
the CT LED next to the wired CT terminal block
is GREEN. If it is RED, verify that the CT is on
the correct phase and/or is installed with the
arrow pointing toward the load. After it is
corrected, the LED will change to GREEN.
Figure 5. Connect White Wire to Positive (+) Terminal.
Connect Black Wire to Negative (-) Terminal.
You are now ready to begin your monitoring session.