5.3 Commissioning procedure (workflow)
This topic deals with commissioning on the VISONIK side. Essentially it consists of the
following:
• Commissioning the NIDES.RX
• Commissioning the RX master
• VISONIK-specific engineering
To commission the NIDEX.RX, proceed as follows:
Step Activity
1 Commission the NIDES hardware as described in data sheet CA2N3299E.
2 Connect the NIDES.RX to the RS master
Notes on connection:
– The NIDES.RX and the VISONIK.BPS are connected via V.24 interface,
to TTY1 (default) or TTY2, as required.
– Serial cable:
RS232 cable, data lines 2/3 not crossed, connector: DB9 female / DB25
female.
The RX master is commissioned using the VISOTOOL Editor. Proceed as follows:
Step Activity
1 Load the following three files into the BPS:
– CFE_V2_x_y.COL (RX master, basic configuration)
– GroupConfig.COL (Group definitions)
– RxNIBPS.COL (Project-specific data)
2 Run Task 125 (Monitoring task) with "RUN125"
Note: If GroupConf.COL or or RxNIBPS.COL are not found, "RUN125" will
result in an error message with the name of the missing task.
The RX master will now load the Infolist into the NIDES. The process can be followed
on the NIDES or the RX master (see "Commissioning procedure (workflow)" on the
next page.
You can then start the VISONIK-specific engineering process. This includes:
– Configuring parameters, e.g. for summer/winter compensation
– Creating time programs
– Text commentary
– Testing
– etc.