Commissioning Instructions
77 / 134
Siemens Synco™ living CE1C2740en
Building Technologies Commissioning the system 13.12.2010
Connect gas shutoff valve
Inform the QAX913 central apartment unit that you want to connect an output
to control a gas shutoff valve:
Main menu > Commissioning > RF connections > Supervision
> Gas shutoff valve > Connect device:
The following devices or device channels can be connected:
• Universal relay output Qx of a multi-controller (see page 65).
• Universal relay
output Qx of a heating circuit controller (see page 62).
• RF adapter plug
KRF960 (see page 72).
Connect status outputs 1 – 4
Inform the QAX913 central apartment unit that you want to connect a status
output:
Main menu > Commissioning > RF connections > Supervision
> Status output X > Connect device:
The following devices or device channels can be connected:
• Universal relay output Qx of a multi-controller (see page 65).
• Universal relay
output Qx of a heating circuit controller (see page 62).
• RF adapter plug
KRF960 (see page 72).
Connect handheld control
Inform the QAX913 central apartment unit that you want to connect a hand-
held control:
Main menu > Commissioning > RF connections > Handheld control
> Handheld control X > Connect device:
Confirm subentry “Connect device“ by pressing the
Menu/ok button. To con-
nect press the binding button on the device to be connected.
2731Z14
2
1
Simultaneously press the upper tow buttons 1
and 2 on the handheld control. The LED lights
up in accordance with the battery charge (blue:
Bat. ok, yellow: Bat not ok). Release the buttons
when the LED starts blinking.
Successful connection is displayed on the cen-
tral apartment unit and confirmed with a beep.
Press the
Menu/ok button to exit the binding
process.