Commissioning Instructions
45 / 134
Siemens Synco™ living CE1C2740en
Building Technologies Commissioning the system 13.12.2010
Heat demand relay
When the appropriately defined output terminal closes, a heat demand signal
is transmitted to the heat source.
Specify if a heat demand relay is used and how it is controlled.
Main menu > Commissioning > Basic configuration
> Outputs > Heat demand relay:
--- Inactive – heat demand relay not needed
(factory setting).
Via RF Relay output Qx of an RRV91… heating circuit con-
troller or RRV934 multi-controller used as a heat
demand relay.
Q1 (local) Relay output Q1 of the central apartment unit used
as a heat demand relay.
Heat demand DC 0..10 V
The current heat demand can be transmitted to the heat source in the form of
a DC 0..10 V signal.
The temperature values corresponding to DC 0 V and 10 V and the threshold
value for a valid heat request can be set (see page 119).
Specify if the DC
0..10 V heat demand output is used and how it is controlled.
Main menu > Commissioning > Basic configuration
> Outputs > Heat dem DC 0...10 V:
--- Inactive – DC 0..10 V heat demand output not re-
quired (factory setting).
Via RF Universal output U of the RRV912… heating circuit
controller or the RRV934 multi-controller used as a
DC 0..10 V heat demand output.
Refrigeration demand relay
When the appropriately defined output terminal closes, a refrigeration demand
signal is transmitted to the refrigeration source.
Specify if a refrigeration demand relay is used and how it is controlled.
Main menu > Commissioning > Basic configuration
> Outputs > Refrig demand relay: