● A higher priority (1-7) must be active to command at priority=1 ( ).
● If priority=1 ( ) is active then a simultaneous active priority=8 ( ) can be released but NOT be reenabled.
Logging test results
1. Click to display the State drop-down list for the point being tested.
2. Select the applicable test result from the drop-down list. (Failed or Passed).
3. Do one of the following:
– If the result is Failed, select a reason from the Comment drop-down list and complete the Tested by and
Assigned to fields.
Note: The comment is transferred to the ABT project following read back of data.
– If the result is Passed, complete the Tested by field.
4. Click Save to save your changes and collapse the row.
Note: The result is stored as a new entry in the commissioning history event log.