Installation Instructions

Document No. 546-14407
Installation Instructions
August 14, 2013
Page 2 of 6 Siemens Industry, Inc.
Figure 1. LCM-OAVS with BTU Compensation, HW Reheat and Two Fast Dampers (One Exhaust, One Supply).
Installation Instructions
NOTE: Follow all safety regulations and local codes
when installing this equipment.
1. Using the mounting rail as a template (Figure
1), mark the screw holes where you will install
the LCM-OAVS.
2. Do one of the following:
If using self-tapping screws, fasten the
mounting rail using a drill and hex nut bit.
If not using self-tapping screws, drill two 1/8-
inch (3 mm) pilot holes, then fasten the
mounting rail with No. 6 or No. 8 screws.
3. With the ESD wrist strap attached to your wrist
and a good earth ground, remove the controller
from the anti-static bag and snap it securely into
place on the mounting rail.
4. If the LCM-OAVS will be used with a field panel,
disconnect the field level network (FLN) trunk
from the field panel.
5. Wire the FLN trunk to the LCM-OAVS (Figure 2).
After all controllers are connected to the FLN,
reconnect the FLN trunk to the field panel.
Figure 2. FLN Trunk Wiring.
6. If the LCM-OAVS requires Offboard Air
Modules, install them now following the
Installation Instructions (550-819).
7. Connect the point wiring. See Wiring Diagrams.
DO WiringEach DO provides a
Normally Open (NO) terminal and a
Common (C) terminal. To reduce noise
and the potential for ground loops, both
connections of a 24 Vac load must be
wired directly to the DO terminals on the
controller board.
The LCM-OAVS DOs control 24 Vac
loads only. The maximum rating is 12 VA
for each DO. Use an interposing 220V