Installation Instructions

Document No. 546-00334
Installation Instructions
December 8, 2011
Information in this document is based on specifications believed correct at the time of publication. The right is reserved to make changes as
design improvements are introduced. APOGEE and Insight are registered trademarks of Siemens Industry, Inc. Other product or company
names mentioned herein may be the trademarks of their respective owners. © 2011 Siemens Industry, Inc.
Siemens Industry, Inc.
Building Technologies Division
1000 Deerfield Parkway
Buffalo Grove, IL 60089-4513
U.S.A
Your feedback is important to us. If you have
comments about this document, please send them
to SBT_technical.editor.us.sbt@siemens.com.
Document No.546-00334
Printed in the USA
Page 5 of 5
Wiring Connections
Several electrical connections must be made from
the field panel, or UC to the terminal to operate the
AOP Transducers and the differential pressure
transmitter.
NOTE: The AOP Transducer used in these steps
is P/N 545-113.
1. Connect a two-conductor 20 AWG cable to
the field panel’s 0 to 10V output or UC’s
universal output. Connect it to the AOP
Transducer connected to the mixing damper
or through the wiring bushing/knockout on
the terminal enclosure (Figure 5) to the AO
P Transducer inside the enclosure. The wire
bushing can be removed and a standard
1/2-inch conduit knockout fitting may be
installed. Connect the cable to the AOP
Transducer (See Figure 6).
2. Connect a two-conductor 20 AWG cable to the
field panel’s 4 to 20 mA input or UC’s universal
input. Connect it to the differential pressure
transmitter (Figure 7) or through the wiring
bushing/knockout on the terminal enclosure
(See Figure 5) to the differential pressure
transmitter inside the enclosure. Connect the
cable to the differential pressure transmitter.
The installation is now complete.
Figure 6. AO-P Transducer Wiring Connections.
Figure 7. Differential Pressure
Transmitter
Wiring Connections.