Specifications

IP 240 Operation
5 Operation
Before startup you must set various coding switches on the module.
You can stipulate
interrupt generation with switchbanks S1 and S2 ( Section 5.1)
disabling of the digital outputs in the event of active BASP signal with switchbank S4
( Section 5.2)
encoder signal matching with switchbanks S5 and S6 ( Section 5.3)
The locations of the switchbanks and the fuses are shown in Fig. 5-1. The switch settings in the
figure are factory setttings.
Fig. 5-1. Locations of Switchbanks and Fuses
F5
F6
F1
F2
F3
F4
S5
S1S2
S4
S6
off on off on
off on
off on
off on
D2
D1
D2
D1
Channel 2
Channel 1
F1 ... F4: Fuses for digital outputs
S1: Setting assignments in PB0
( Chapter 5.1.2)
S2: Setting interrupt generation
( Chapter 5.1)
Setting address range
( Chapter 3)
S4: Setting sensor type sym./asym.
( Chapter 5.3.1)
Setting response to BASP
( Chapter 5.2)
S5/S6: Setting the sensor signal level
for channel 1 (S1) and
channel 2 (S6) ( Chapter 5.3.2)
F5: Fuses of the 5 V sensor supply
F6: Fuse of the 24 V sensor supply
X6
X1
X2
X3
X4
X5
S3
EWA 4NEB 811 6120-02a
5-1