Installation Instructions
Document No. 541-865
Installation Instructions
Rev. 4, March, 2000
Page 10 of 10
Siemens Building Technologies, Inc.
When the BRU COMPLETE message displays,
remove the Revision K.0 Master tape from the
drive.
21. Boot the system.
Press
ALT+C
Choose
4
from the CoProcessor Control Menu
to return to DOS.
Edit OSPREY.CNF and change the
configuration back to Auto Boot.
Enter
OSPREY
at the DOS prompt and press
<RETURN>
; the system will begin to boot.
The following prompt displays:
DU0 IS THE PRIMARY DRIVE
DU1 IS THE SECONDARY DRIVE
* IS THE ABOVE CORRECT? [Y/N]
Type
Y
at this prompt and press
<RETURN>
.
Ignore any errors that may occur setting up the
TT devices.
When the time prompt appears, abort the start-
up. If a battery backup clock is installed, then
wait for the clock to answer the time prompt
before aborting the start-up. To abort the start-
up, do the following:
Press
CTRL+C
Type
ABO AT.
and press
<RETURN>
.
22. Type the current time and date as you did in
Step 18.
23. Insert and load the cartridge containing the old
copy of the job site software in the drive.
24. The following steps should be run from a hard
copy device (e.g., MCR printer) to aid Field
Support if problems arise.
25. Begin the conversion process. Type
@[3,352]REVK
and press
<RETURN>
.
The system converts your current system from
Revision J.8 or pre-release K.0 to Revision K.0.
During this procedure, you are required to
respond to several prompts. When your input is
required, two beeps sound and a question
displays at the Revision K.0 prompt (
REVK.0>
).
Read the question and the accompanying
information. Provide the appropriate information
for your system type. Continue to read and
respond to all prompts. When the conversion
process is complete, the following message
displays:
REVISION K.0 UPDATE PROCEDURE
COMPLETE
26. When the conversion is complete, mark the old
cartridge with the proper revision name
(Revision J.8 or pre-release K.0) and save it for
at least 4 weeks. The old cartridge can be used
for a system backup after that time.
27. Run
$SHUTUP
and then reboot the system.
After the system has been booted, run basic
tests to verify that the conversion process has
been successful and that Revision K.0 is
working properly. You should make a backup
using [3,352] TAPEBACK command file as soon
as possible.
28. The original Revision K.0 cartridge should be
returned to the Branch where it can be used for
additional conversions for this system type to
Revision K.0.
29. After the K.0 installation is complete, BRU DU0:
to tape and then BRU the tape back to DU0: to
recover contiguous space.
Expected Installation Time
Conversion from:
Revision J.8: 4.0
hours.
Revision K.0 (Pre-release): 3.5 hours.