Technical data
Commissioning with PROFIBUS
3.5 Example of first commissioning with STARTER
Function Manual
Function Manual, 06/2012, 6SL3097-4AB10-0BP4
57
What to do? How to do it?
You have now created the project.
→ Click "Complete".
4. Summary
5. Configure the drive
unit.
Once you have created the project, you have to configure the drive unit. The "Example of first
commissioning using STARTER" chapter contains an example scenario.
3.4.3 Searching for nodes that can be accessed
To search for a drive unit online, the drive unit and the PG/PC must be connected via
PROFIBUS. The interface must be set correctly in STARTER.
3.5 Example of first commissioning with STARTER
The example provided in this section explains all the configuration and parameter settings
that are required for first commissioning. Commissioning is carried out using the STARTER
commissioning tool.
Requirements for commissioning
1. The checklist for commissioning (Table 1-1 or 1-2 in Section 1.1) has been filled out and
the points ticked off.
2. STARTER is installed and activated.
→ See the "Readme" file on the STARTER installation CD.
3. The power supply (24 VDC) is switched on.