Technical data
  Safety Integrated Functions 
  8.9 Acceptance test and acceptance report 
Function Manual 
Function Manual, 06/2012, 6SL3097-4AB10-0BP4 
467 
8.9.2.3  Test scope for specific measures 
Table 8- 21  Scope of partial acceptance tests for specific measures 
Measure  A) Documentation  B) Functional testing 
of safety functions 
C) Functional testing 
of forced dormant 
error detection 
D) Functional 
testing of actual 
value acquisition 
E) Conclusion 
of the report 
Replacement of 
the encoder 
system 
Yes, Points 1 and 2  No  No  Yes  Yes 
Replacement of 
an SMC/SME 
Yes, Points 1 and 2  No  No  Yes  Yes 
Replacement of 
a motor with 
DRIVE-CLiQ 
Yes, Points 1 and 2  No  No  Yes  Yes 
Replacement of 
the Control Unit 
/ power unit 
hardware 
Yes, Points 1 and 2  No  Yes, only Point 1  Yes, only Point 1  Yes 
Replacement of 
the Power 
Module or Safe 
Brake Relay 
Yes, Points 1 and 2  Yes, Points 1 or 2 
and 3 
Yes, only Point 1  Yes, only Point 1  Yes 
Firmware - 
upgrade(CU/po
wer unit/ Sensor 
Modules) 
Yes, only Point 2  Yes, if new safety 
functions are to be 
used 
Yes  Yes, only Point 1  Yes 
Change to a 
single 
parameter of a 
safety function 
(e.g. SLS limit) 
Yes, Points 4 and 5.  Yes, test the 
appropriate function 
No  Yes  Yes 
Transfer of 
project data to 
other machines 
(series 
commissioning) 
Yes  Yes, but only testing 
of the selection of the 
safety functions 
Yes  Yes  Yes 
Note 
Forced dormant error detection functional testing (C) and actual value acquisition functional 
testing (D) together represent the "simplified function test" mentioned in previous chapters. 