Commissioning Instructions
Automatic Demand Shed
37
Unrestricted
A6V12035398
Automatic Demand Shed
See 2019 nonresidential Compliance Manual section 4.5.1.6 for more information,
section 13.14 NA7.5.10 for acceptance criteria and NRCA-MCH11-A for acceptance
test form. In summary, if this acceptance form is required (box checked on the Title 24
sheet), all controls systems with DDC to the zone level are required to enable
centralized demand shed at non-critical control zones from either a single software or
hardware point in the system.
ยง120.2(h) Automatic Demand Shed Controls. HVAC systems with DDC to the Zone level shall
be programmed to allow centralized demand shed for non-critical zones as follows:
1. The controls shall have a capability to remotely setup the operating cooling temperature set
points by 4 degrees or more in all non-critical zones on signal from a centralized contact or
software point within an Energy Management Control System (EMCS).
2. The controls shall have a capability to remotely set down the operating heating temperature
set points by 4 degrees or more in all non-critical zones on signal from a centralized contact or
software point within an EMCS.
3. The controls shall have capabilities to remotely reset the temperatures in all non-critical
zones to original operating levels on signal from a centralized contact or software point within an
EMCS.
4. The controls shall be programmed to provide an adjustable rate of change for the tempera-
ture setup and reset.
5. The controls shall have the following features:
A. Disabled. Disabled by authorized facility operators; and
B. Manual control. Manual control by authorized facility operators to allow adjustment of heating
and cooling set points globally from a single point in the EMCS; and
C. Automatic Demand Shed Control. Upon receipt of a demand response signal, the space-
conditioning systems shall conduct a centralized demand shed, as specified
The DXR has a central function that can be used to meet this requirement called
Central Setpoint Shift that is under the Central Operating Mode. In addition,
supervisory PPCL will be required to implement Automatic Demand Shed.