User Manual
Configuration
Reports
4
22 | 36
A6V11938631_en--_a
1. Click on a line item to display the data point test options.
2. Select the applicable test result from the drop-down list, (Failed or Passed).
3. Do one of the following:
– If the result is Failed, select a reason from the Comment drop-down list, and complete the Tested by and
Assigned to fields.
– If the result is Passed, complete the Tested by field.
4. Click to save your changes and collapse the row, or click to cancel.
NOTE: Saved results are logged as new entries in the Commissioning history event log.
4.3 Reports
The following reports can be displayed, printed and / or saved to an Excel spreadsheet (.xls):
● Commissioning
● Data point test
Commissioning
The Commissioning report contains detailed information on the automation station’s connected field buses.