Engineering Documentation
Table Of Contents
- Copyright Notice
- 1 About this document
- 2 Desigo Control Point Operation engineering topics
- 2.1 Tool-free configuration of a Desigo Control Point device
- 2.1.1 Connecting to the Desigo Control Point device
- 2.1.2 Performing the initial login
- 2.1.3 Configuring the Network port for IP (PXG3.Wx00 and PXM… touch panel)
- 2.1.4 Activating the application (PXG3.Wx00 and PXM… touch panel)
- 2.1.5 Assigning devices to the Desigo Control Point device
- 2.1.6 Updating the Network port for a browser connection (PXM… touch panel)
- 2.1.7 Subscribing to the time master and time synchronization for Assigned devices
- 2.1.8 Configuring for kiosk graphics on a touch panel
- 2.2 Tool-free commissioning of the Operation application
- 2.3 Data point integration overview
- 2.4 Plant view Tools
- 2.4.1 Using the graphics wizard to create a graphic
- 2.4.2 Editing a graphic
- 2.4.3 Removing a graphic
- 2.4.4 Displaying the URL of a graphic
- 2.4.5 Exporting graphics for sharing across jobs
- 2.4.6 Importing graphics
- 2.4.7 Enabling graphics and kiosks for room users to view
- 2.4.8 Defining graphics as a startup page
- 2.5 Working with kiosk graphics
- 2.6 Using engineering notations
- 2.1 Tool-free configuration of a Desigo Control Point device
- 3 Graphics engineering with Graphics Builder
- 3.1 Graphics Builder overview
- 3.2 Using the Builder pane tools
- 3.3 Graphics libraries
- 3.4 Workflows
- 3.5 Working with dashboards
- 3.5.1 The Facility manager dashboard user interface
- 3.5.2 The Public dashboard user interface
- 3.5.3 Adding and editing a text box
- 3.5.4 Adding or replacing a background image
- 3.5.5 Adding information from a trended data point
- 3.5.6 Adding external media to a dashboard
- 3.5.7 Working with gauges
- 3.5.8 Editing charts
- 3.6 Creating end-user room graphics
- 3.7 Advanced functionality
- 4 Tips and tricks
- 4.1 Updates required after a time zone change
- 4.2 APPLY BATCH TAGS > Custom Filter button is reserved for future use
- 4.3 Graphic components within models cannot be modified
- 4.4 A graphic with relative binding that includes data points from different branches of the hierarchy cannot be created at the Root level
- 4.5 Relative hyperlinks cannot be added to a graphic at the Root level
- 4.6 Relative hyperlinks in a graphic are broken if the graphic is engineered offline and then imported to another device
- 4.7 Haystack interface
- 4.8 Automatic logout from the Operation application causes Graphics Builder to temporarily stop working
- Index
Desigo Control Point Operation engineering topics
Data point integration overview
27 | 138
Siemens
A6V11211560_enUS_b
Building Technologies
2019-01-15
2.3.1 Data point integration user interface
①
Desigo Control Point device description and % of device capacity that is used by integrated data
points
The model of Desigo Control Point device determines the total number of BACnet objects that can
be integrated.
②
Default integration level
The default integration level is configured in the Data point integration settings and applies to DXRs
only.
To set the Integration level field for all DXRs in the list to your selected default, click Apply to all.
Note
All data points are integrated for non-DXR BACnet devices, regardless of the integration level.
③
Integrate button
Starts the integration process. This button is enabled when at least one device is selected.
Note
The integration process stops if the number of data points being integrated exceeds the device
capacity.
④
Close button
Click to close the data point integration function.
⑤
Device selection check box
Select individual check boxes or the Select all check box to select devices for data point integration.
The cursor changes to Not available if the device is not available or not ready for data point
integration.
⑥
Device
Description of the device being monitored.
⑦
Device state
Indicates the availability of each device for data point integration. See the following Table
Device
state indications
for more detail on each state.
⑧
Status
Indicates whether the objects from the device have been integrated to the Desigo Control Point
device for monitoring. See the following Table
Status indications
for more detail on each status.