Operating instructions

Commissioning
5.5 Commissioning using the BOP
Control Units CU240S
60 Operating Instructions, 10/2007, A5E00766042B AC
5.5.2 Overview Commissioning with the BOP
Commissioning overview
A differentiation is made between the following scenarios when commissioning the inverter
via BOP:
Single commissioning
Basic commissioning
Quick commissioning
Motor data identification
Speed control optimization
Further settings for commissioning
Calculating the motor/control data
Commissioning the application
Reset parameters to factory settings
Commissioning the fail-safe functions (only in fail-safe applications)
Series commissioning
Uploading the parameter set
Downloading the parameter set
When commissioning, initially, a quick or series commissioning should be performed.
If there is no appropriate parameter set available for series commissioning, a quick
commissioning must be carried-out.
With the function "quick commissioning", the inverter is adapted to the motor and important
technological parameters are set.
The function "commissioning the application" should only be performed, if the inverter–motor
combination provides a satisfactory result.