Operating instructions
Commissioning
5.5 Commissioning using the BOP
Control Units CU240S
60 Operating Instructions, 10/2007, A5E00766042B AC
5.5.2 Overview Commissioning with the BOP
Commissioning overview
A differentiation is made between the following scenarios when commissioning the inverter
via BOP:
Single commissioning
● Basic commissioning
– Quick commissioning
– Motor data identification
– Speed control optimization
● Further settings for commissioning
– Calculating the motor/control data
– Commissioning the application
– Reset parameters to factory settings
● Commissioning the fail-safe functions (only in fail-safe applications)
Series commissioning
● Uploading the parameter set
● Downloading the parameter set
When commissioning, initially, a quick or series commissioning should be performed.
If there is no appropriate parameter set available for series commissioning, a quick
commissioning must be carried-out.
With the function "quick commissioning", the inverter is adapted to the motor and important
technological parameters are set.
The function "commissioning the application" should only be performed, if the inverter–motor
combination provides a satisfactory result.