Operating instructions
Commissioning
4.5 Commissioning with STARTER
CU240S and CU240E Control Units, FW 3.2
58 Operating Instructions, 03/2009, A5E02440075B AA
4.5 Commissioning with STARTER
Prerequisites
The STARTER commissioning tool features a project Wizard that guides you step-by-step
through the commissioning process. Configuring the inverter using the PC is significantly
more user friendly and faster than commissioning using the operator panel.
The following is required to commission the inverter via the PC:
● A PC connection kit for connecting the inverter to a PC.
Order no.: 6SL3255-0AA00-2AA1
Figure 4-3 PC connection kit
● The installed STARTER software.
(supplied with the PC connection kit). You can download the latest version from the
Internet under the following address
(http://support.automation.siemens.com/WW/view/en/10804985/133100
):
● The motor must be connected to the inverter.