Operating instructions
Servicing and maintenance
6.4 Standard commissioning
CU240S and CU240E Control Units, FW 3.2
218 Operating Instructions, 03/2009, A5E02440075B AA
6.4 Standard commissioning
Standard commissioning with a valid parameter set
If you have a memory card with a valid parameter set, then you can also perform standard
commissioning for several inverters.
Prerequisites
● Several inverters (Control Units and Power Modules of the same type) must be
commissioned for the same application.
● A memory card with a valid parameter set is available.
Procedure for standard commissioning
1. Insert the memory card into the control unit of the first inverter.
2. Switch-on the inverter power supply (the valid parameter set is downloaded into the
inverter from the memory card)
3. Wait until the inverter has completely booted (RDY-LED and SF-LED are lit, BOP returns
to the standard display)
4. Remove the memory card and acknowledge message F0395 (SF-LED is dark)
5. Proceed with the next inverter