5.4.2 Start quick commissioning and select the application class
Starting quick commissioning
Preconditions
The power supply is switched on.
The operator panel displays setpoints and actual values.
Procedure
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
To start quick commissioning, in the "SETUP" menu, press the OK key.
If you wish to restore all of the parameters to the factory setting before the quick commissioning,
proceed as follows:
1. Press the OK key.
2. Switchover the display using an arrow key: nO → YES
3. Press the OK key.
Selecting the application class
Whether the inverter offers the selection of the application class, depends on the Power Module
being used:
PM230 or PM250 Power Modules:
The inverter skips step DRV APPL.
PM240‑2, PM240P‑2 or PM330 Power Modules:
select the application class:
Quick commissioning with application classes (Page 166)
Select the motor standard:
KW / 50HZ: IEC
HP / 60HZ: NEMA
KW / 60HZ: IEC 60 Hz
Specify the overload capability of the inverter:
HIGH OVL: Load cycle with "High Overload"
LOW OVL: Load cycle with "Low Overload"
Overload capability of the inverter (Page 444)
63 
6(783
5(6(7
3
'59$33/
3
(8586$
3
/2$'7<3
Commissioning
5.4 Quick commissioning using the BOP-2 operator panel
Converter with the CU230P-2 Control Units
160 Operating Instructions, 04/2018, FW V4.7 SP10, A5E34257946B AF