Installation Instructions
Document No. DPD01375
Installation Instructions
August 24, 2018
Page 30 of 36
Siemens Industry, Inc.
NOTES:
1. Incoming power phase rotation should be L1, L2, L3 to match inverter forward direction phase rotation U, V, W. Connection as
shown should produce clockwise direction when viewing the motor from the shaft end. Always test motor direction in both drive and
bypass modes before coupling the motor to the load.
2. 100kAIC SCCR achieved only when customer branch circuit protection is installed using the specified fuses from Table 8.
3. F2 not present in FS4.
Figure 40. Bypass Power Circuit, Disconnect with Fuses Version, FS4 and FS6.
NOTES:
1. Incoming power phase rotation should be L1, L2, L3 to match inverter forward direction phase rotation U, V, W. Connection as
shown should produce clockwise direction when viewing the motor from the shaft end. Always test motor direction in both drive and
bypass modes before coupling the motor to the load.
2. 100kAIC SCCR achieved only when customer branch circuit protection is installed using the specified fuses from Table 8.
3. F2 not present in FS5.
Figure 41. Bypass Power Circuit, Disconnect with Fuses Version, FS5.