Operating Instructions
Demonstration Panel Overview
3
Operation Overview
15
Siemens Industry, Inc. 125-1007 Rev.BA
2014-08-14
Electronic Bypass Configuration Notes:
A jumper between Terminals 3 and 4 of the diagnostics board (pre-installed) is
required. On the BT300 Demonstration Panel, this is wired to an SPST toggle
switch for convenience. The switch is labeled
Override Safety and is mounted to
the left of the diagnostic board.
The Drive should be factory reset.
The Bypass Wizard should be run.
Drive (Auto or Hand) will close the output (M2) contactor. The bypass (M1)
contactor will be open. The motor will spin in accordance with drive operation.
Off will open the bypass (M1) and output (M2) contactors. The motor will be unable
to spin.
Bypass will close the bypass (M1) contactor. The output (M2) contactor will be
open. The motor will be connected to utility/line power.