Installation Instructions

Document Number 540-1033
Installation Instructions
October 26, 2016
Page 4 of 6 Siemens Industry, Inc.
5. Do one of the following:
If you updated the initial values from the old
controller at the field panel, then when you
set the address and application for the new
controller, the field panel will automatically
send the initial values down to the new
controller. Once this takes place,
replacement is complete.
If you manually recorded the initial values in
the table, then enter them into the new
controller. If a field panel is present, then
update the controller’s initial values. The
replacement is complete.
If there was no communication at the old
controller, or the new controller has a newer
firmware revision than the old controller,
then enter the initial values into the new
controller. At the field panel, add the LCTLR
point and update the controller’s initial
values. The replacement is complete.
Figure 2. RPC with Autozero Modules.
Figure 3. Mounting Dimensions.
Figure 4. FLN Wiring.