Installation Instructions

Document No. 545-406
Installation Instructions
January 23, 2004
Information in this publication is based on current specifications. The company reserves the right to make changes in specifications and
models as design improvements are introduced. Other product or company names mentioned herein may be trademarks of their respective
owners. © 2004 Siemens Building Technologies, Inc.
Siemens Building Technologies, Inc.
1000 Deerfield Parkway
Buffalo Grove, IL 60089-4513
U.S.A.
Your feedback is important to us. If you have
comments about this document, please send
them to technical.editor@siemens.com
Document No. 545-406
Printed in the U.S.A.
Page 4 of 4
Installing the AO-P Module
Do the following for each AO-P module being
installed:
1. Use the MBC layout sheet and address keys
and markers to match the AO-P module to the
appropriate connector block.
2. Remove any M-BUS protective tape that was
not removed when the connector block was
installed.
3. Align the AO-P module mounting guides with
the right edge of the M-BUS rail (Figure 7).
4. Rotate the free end of the module so that it
mates with the previously installed connector
block.
5. Verify that the module is aligned with the
connector block and firmly press the AO-P
module into place.
The AO-P module snaps into the connector
block with a light “click.
CAUTION:
The AO-P module should easily snap into
place. If not, recheck the alignment of the
mounting guides with the M-BUS rail.
Repositioning or Removing an AO-P Module
1. While pressing the AO-P module toward the
connector block, push the module housing
release tab located on the left side of the AO-P
(Figure 8).
2. Tilt the AO-P module out of the M-BUS rail
(shown in Figure 8).
Completing the Installation
1. Leave the layout sheet in the literature pocket
located at the bottom of the enclosure.
2. Use tie-wraps to secure Return (R) line(s) to the
cable tie bar.
For MBCs with Styled Doors and RBCs with
Windowed Doors
Remove the perforated blank-out papers from the
view panel to expose each AO-P module location.
The installation is now complete.
Figure 7. Installing an AO-P Module.