Product Description
This Laboratory Room Controller (LRC) features
VAV control of a laboratory room with one supply
duct, one exhaust duct, and up to four Fume Hoods.
It uses fast-acting electronic actuators (shipped
separately) to control the supply and exhaust venturi
air valves. The LRC can operate stand-alone, with a
field panel, or as part of a network. If CE compliance
is desired, a ferrite filter and an alternate room
temperature sensor cable must be used (see
Product Numbers).
This LRC can be ordered with or without Air Velocity
Sensor (AVS) transducers mounted on the board. If
ordered without AVS transducers mounted on the
board, two Remote Air Modules (RAM) are required.
Shipping carton contains a controller assembly
(controller board and cover), a mounting rail, and
two self-tapping screws.
NOTE: Keep the controller in its static-proof bag
until installation.
Product Numbers
Product Description
546-14323A
LRC with HW Reheat and Two Venturi Air
Valves—onboard AVS
550-767B
LRC with HW Reheat and Two Venturi Air
Valves—offboard AVS (requires two Remote
Air Modules)
550-818A
Remote Air Module (two required—ordered
and shipped separately)
The LRC is designed to work with fast-acting electronic
actuators (order separately).
Parts for CE Compliance
588-100A 25-ft (7.6 m)
588-100B 50-ft (15.2 m)
588-100C
2-RJ11 room sensor
cable with alternate
twisted pairing
100-ft (30.48 m)
550-705 clamp-on ferrite filter 10 pack
Installation Conventions
CAUTION
Equipment damage or loss of
data may occur if user does not
follow procedure as specified.
Required Tools
Electro-Static Discharge (ESD) wrist strap
Small and medium flat-blade screwdrivers
Electric drill
1/4-inch (6.35 mm) hex nut bit
Additional tools if not using self-tapping option:
1/4-inch nut driver
1/8-inch (3 mm) bit
Prerequisites
Wiring conforms to NEC and local codes
and regulations.
Floor level network (FLN) with 24-volt wiring.
Supply power to the unit OFF.
Any necessary hardware installed: terminal
unit, actuator(s), sensor(s), etc.
Room Temperature Sensor (RTS) installed
(optional). Note: a low-cost temporary RTS
(P/N 540-658P25) is available that plugs into
the RTS port on the LRC, providing
temperature input and actual space control
until a permanent RTS is installed.
Expected Installation Time
New controller installation 10 min.
Replacement with removable
terminal blocks
6 min.
Replacement without removable
terminal blocks
16 min.
NOTE: You may require additional time for
database work at the field panel.