Installation Guide

Selecting locations for gateways
We will provide a map with a recommended placement for each gateway (example below). You
will need to identify a suitable pole or other piece of infrastructure that is appropriate for
gateway mounting, as close to the recommended location as possible.
VI. Installing gateways
First, you will be installing gateways that manage communications between Pebbles and the
server. It is important to install the gateways first because Pebbles that are activated out of
range of a gateway will drain battery faster than normal while searching for a gateway pairing.
We estimate that installing gateways should not take longer than 45 minutes per gateway, but
will depend heavily on the installation location and equipment required to access it.
Below are the steps for installing gateways:
1. Mount the gateway
a. Select a mounting location and orientation. If possible, the gateway should be
mounted with the solar panel facing south (orientation does not need to be exact,
but effort should be made to expose the panel to as much light as possible)
b. Using the pole mounting kit, attach the metal brackets to the outer flange on the
top and bottom of the enclosure using a nut/bolt assembly
c. Attach the gateway to a pole (with the two longer antennas pointing ), by
running the hose clamp through the slots on each metal bracket, wrap around
pole, and thread back through a slot on the bracket
d. While holding the enclosure tight against the pole, tighten the clamp with 5/16in
(8mm) nut drive
Sidewalk Labs Confidential and Proprietary Page 8 of 16