User Manual
Shenzhen Lean Kiosk Systems Co., Ltd
9 Add: Fu'an Industrial Area, Dayang Road, Fuyong Town, Baoan District, Shenzhen, Guangdong Province, China.
Stock Code
:
870885
2. The power cord and network cable will go through from the bottom /base of the kiosk then enter into
the kiosk cabinet, and the ground installation platform should pre-set the entrance hole for the cables in
advance.
3. Since there are drain-pipes from air conditioner and dehumidifier inside the kiosk bottom, the ground
installation platform for the kiosk must be designed and reserved smooth drainage holes in advance.
4. Corrosion resistant and flame-retardant PVC pipes shall be used for the wire and drain holes inside
the base.
5. Since the weight of the kiosk is measured by is 121 pound, it should ensure that the kiosk is firmly
installed on the street and will not tilt or shift under the thrust of 1,200 pounds.The dimensionof kiosk base is
measured by feet, it should ensure that the installation platform must be poured with cement in enough depth.
6. Since 4 pieces mounting holes with φ0.6inch diameter are reserved at the bottom of kiosk, the
construction personnel just need to use 4 pieces φ0.47inch*4inch stainless steel expansion anchor bolt to
fix the kiosk into the installation platform.
Hole Dimensions of Cement Base
Standard cement base mounting hole size:5.4 inch * 4.3inch