Step 5: Install Cover Rail
Step 6: Attach & Secure Base Feet
Step 7: Install Auger Anchors
Step 8: Panel Installation
Attach the #12191 cross rails using the
3-Way and 4-Way cover rail clamps around
the uprights and losely fasten with 1/4" x 2"
Bolts and Nuts. Check the rails are evenly
spaced above the ground on both sides.
Push down on the connect-ors one at a time
to tension the cover and tighten the bolts to
hold tightly. Fig. 5 & Fig. 6.
Fig. 5
Fig. 8
Fig. 7
Fig. 6
Depending on the model you have purchased, your base feet wil-
leither t onto the outside of the leg poles, or slide inside the leg-
poles. After installing Base Feet Plates onto bottom of Middleleg
Poles,be sure to line up the pre-drilled hole in the leg withthe pre-
drilled hole in the base foot. Insert 1/4" x 2 1/2" bolts all theway
through leg and foot, to other side, secure with nuts. Fig. 7.
Note: The feet should sit reasonably at on the ground.
You will secure the anchors to the corner leg bendsusing the ca-
ble and clamp. Be sure to put cable throughthe hole in the corner
leg bend, and through eye ofanchor, secure with clamp. Repeat
process attaching theremaining anchors to the middle ribs with
the cable around the upright above the foot plate.
Note: Anchors must be placed inside of shelter.
Starting from the peak, remove the cross pole from
the 3-way top connector. Place exposed rope at the
top of the panel over the 3-way connector and under
the cross pole as shown in Fig. 9. Replace the cross
pole. At each corner, remove the cross poole and
fold the fabric around to the inside placing the 3-way
socket through the opening in the fabric as shown in
FIg. 10. Tighten the panel by inserting the “S” hooks
into the holes inthe corner legs, pulling and tying
off as shown in Fig. 11. Repeat step 8 for another
2-zipper door.
1013
1011
1010
10023
1013
10022
1011
1010
clamps
clamps
middle
leg
corner
leg
Secure with
Bolt & Nut
Fig. 9
Fig. 10
Fig. 11