8' W x 8' H or 10' H Peak Style Frame Assembly Assembly Instructions Before you start: 2+ individuals recommended for assembly, approximate time 3 hours. Recommended tools: Power Drill, Safety Glasses, Rope, Tape Measure, Ratchet with Socket Set, Adjustable Wrench, Step Ladder, Rubber Mallet, Utility Knife, 5/8 Concrete Drill Bit, Sledge Hammer. ShelterLogic, LLC 150 Callender Road Watertown, CT 06795 www.shelterlogic.
8'W x 8'H Peak Style Frame Assembly Please read and understand instructions completely before assembly. Layout out frame parts as shown.
8'W x 10'H Peak Style Frame Assembly Please read and understand instructions completely before assembly. 21/22 top rail Layout out frame parts as shown. 13 end rib 21/22 24 8 8' W X 10' H 9 2 middle ribs 21/22 18 7 3 11 24 16 5 13 24 19 25 1 24 17 25 25 5 1 20 16 25 24 24 24 20 24 10 20 7 3 5 3 17 3 4 end rib 19 8 19 4 19 4 CROSS rail 14 5 12 6 10 24 6 15 23 25 UPRIGHT EXTENSION, 27” SWEDGED-1 SIDE 1 5/8 D.
ASSEMBLY OF PEAK STYLE GARAGE SHELTER NOTE FOR FRAME EXTENSION KIT: 8’ x 8’ is the base frame dimension. Your model may have more middle ribs than shown in the illustrations. You will receive one extra rib for every extra 4 feet of building length that you purchase. The basic frame assembly will remain the same. The cover will be the correct size for the length of the building ordered. 8' 1. Plotting and squaring up the Frame: A.
3. Install Side Rails and ShelterLock™ Stabilizer Blocks: A. Place assembled first end rib in the staked area. Place the ShelterLock™ on the upright as shown in Detail D. From the outside of the rib insert the bolt through the upright and then through the ShelterLock™. 02030 DETAIL D B. Place the plain end of the side rail over the bolt and nest it into the ShelterLock™. Install the nut onto the bolt and tighten. Repeat these steps for the opposite side and all of the remaining ribs.
. Secure Base Feet: DETAIL G A. Slide leg pipe over over the base feet, line up the holes in the pipe with the holes in the feet and secure with the hardware indicated in Detail G. 01010 Secure with bolt and nut 10114 7. Install Auger Anchors: A. Anchors must be placed inside shelter. Start at the corners of the shelter. Insert a ¾” pipe or steel rod, through the eyelet of the auger and screw the anchor into the ground. (If ground is too hard, dig a hole with a shovel or post hole tool.
9. Installing the Cover on the Frame: A. Lay the cover on the ground next to the frame with the inside of the cover (the side with the pipe pockets) facing down and the webbing on the front and rear of the corner of the building. Position the cover so that it is centered on the frame, front to back. See Detail K. B. Fold over the side so the pipe pocket is now accessible. Insert a cover pipe into the pipe pocket slot, at the first middle rib from the front and the first middle rib from the rear.
10. Securing Your Cover: A. Install the “S”- hook from the ratchet assembly into the legs of the shelter. Pull the webbing carefully to remove the slack from the cover. Do not to pull the webbing through the opposite side of the cover. B. Insert the webbing through the spindle of the ratchet and pull tight. See Detail O. Wind the ratchet until the webbing overlaps itself. Repeat these steps on the opposite side, then repeat this on the back side of the shelter. C.