Installation Guide

REV.1 1 - 8 - 10
6
Bond Test:
To determine if a subfloor is compatible to Shaw adhesives, or to determine if the porous or non-porous
adhesive application method is required, use this test: Using the flooring and adhesive suitable for the
subfloor, install a 2’x2’ section following the recommended installation procedures Select areas next to
walls, columns, or other light traffic areas. Tape the perimeter with duct tape to prevent edge drying of
the adhesive. After 48 hours, the adhesive should be dry and the flooring should be difficult to remove.
Note: the adhesive is dry at this point but not cured. Full cure and maximum bond does not occur for 6-
8 days. On large installations, tests should be taken every 50 feet. Bond testing may take some time to
complete, but the cost and time involved in a floor failure are considerably more.
General:
For best results, the room temperature in the area of installation must be 65-85° F for 48 hours before,
during, and after installation. Flooring must be acclimated in the room they are to be installed in for a
minimum of 24 to 48 hours prior to installation. Be sure to use Shaw tiles of the same color lot for best
color matching. Mix tile from several different cartons to blend minor shade variations. If the Shaw Tile or
Plank has directional arrows follow accordingly if not lay tile and planks keeping the embossing of the
product flowing in the same direction.
Note: All Warranties and guarantees regarding the suitability and performance of any products, if not
supplied by Shaw, rests with the material manufacturer or the installation contractor and Not with Shaw
IMPORTANT TIPS:
All Concretes (old or new) should be tested for possible moisture.
Underlayments should be APA underlayment grade. Use only Portland-Cement base
patching and leveling compounds.
Room temperature should be between 65° and 85 ° Fahrenheit. Maintain proper
temperature for 48 hours before and after installation.
Materials and Adhesive should be allowed to acclimate for a minimum of 24 to 48 hours.
Use only the appropriate Shaw Adhesive.
All installations must be rolled with a minimum 100 lb roller.
.
If tiles and plank products are to be installed as a combination, it is imperative to make sure that these
products are of the same gauge.