Installation Manual
Table Of Contents
- Table of Contents
- Table of Tables
- Table of Figures
- 1. About this Manual
- 2. Safety
- 3. Package Removal and Inspection
- 4. Installation
- 5. Electrical Connections
- 5.1 The Overview of Electrical Connection
- 5.2 Opening the Front Case Cover
- 5.3 The Overview of the Connection Area
- 5.4 Battery Installation
- 5.5 Inner Wiring Connection (Power and Signal Wire Connection for BMS)
- 5.6 Closing the Front Case Cover
- 5.7 A Method of Locking the Distribution Box (Board)
- 5.8 An Installation Method of Energy Meter Electrical Connection
- 5.9 A Connecting Method of the DC Line from the PV
- 6. Communication Connection
- 7. Entering Initial Installation Information
- 7.1 Information Input Administrator
- 7.2 System Information input stage
- 7.3 PC Direct Connection and Local Setting Value
- 7.4 Web Page Connection
- 8. Operation Test
- 9. Problem Confirmation
- 10. Maintenance
- 11. Technical Specifications
- 12. Disassembly
- 13. Contact
8. Operation Test
8. Operation Test
8.1 Starting the System
After completing the installation, turn on the AC circuit breaker and the DC disconnect
switch installed in the distribution box. (See the Section 5.7)
Check the system check message on the front LCD screen.
[Figure 8-1: Initial indication screen on power on]
After finishing the system check, check the system, the PV, and the battery status.
[Figure 8-2: Standby state indication screen before the EMS command]
You will receive the command from the EMS to convert to operation mode.
For individual operation mode screen, refer to 8.3.
If there is an event message received, refer to 8.3.7.
8.2 Turning off the System
To turn-off the system, push down the manual AC circuit breaker and the DC disconnect
switch in the distribution box.
United Kingdom (Eng.) 05/2015. Rev1.1 59