Operating Manual

Installation, assembly and commissioning for
the first time
Version 1.1 Page 43 of 92
5 Insert the housing cover in the housing and tighten the screws of the cover.
For this purpose, use 2
DIN 7985 M4x6 fillister-head screws. Fix these using a PH2 Phillips screwdriver and a
maximum tightening torque of 2.5 Nm (tolerance: +/-0.1 Nm).
Figure 4-9: battery storage system, side view
The cover may remain open during the first installation in order to switch on the battery. Close the cover after
switching on the battery
6
Execute the first commissioning process by following the specifications from the Operation section (page 76).
7
Configure the parameters of the inverter as mentioned in section 4.18 (Recommended parameters).
Ensure that the batteries are not earthed by mistake. If they are earthed, disconnect the corresponding
connection.
Check all parts for firm fitting. Re-tighten all screws and terminals.