Technical data
Rev.February 1996 Conti-Dryer Page 19
CD 25-600
Diode, overtemperature (23)
Diode giving signal if current temperature
is 12° C (35°F) above/below set temperature.
4.5 Adjustment
1. Adjust required drying temperature on the
temperature controller (13)
2. Adjust air intake on top of the fi lter by
turning the fresh air valve (5).
Maximum = full fresh air intake
Minimum = lowest air intake and major
recirculation share
R1634
As a start the fresh air valve is adjusted in
the middle of the interval. Adjust until
required drying result is achieved.
4.6 Start
1. Close slide valve (24) in bottom of drying hopper.
2. Charge hopper either manually or by means of an attached Con-Evator.
3. Required drying temperature is adjusted on temperature controller (13).
4. Use main switch (18) to connect power.
5. Wait recommended drying time (see capacity table).
6. The slide valve (24) in bottom of drying hopper can now be opened, and production
set going.
4.7 Operation
If the CD is used for batch drying, the hopper must be recharged whenever empty by turning
off the drying apparatus and follow the above described start procedure.
If the CD is used in continuous operation with Con-Evator attached, the drying hopper is
charged automatically pari passu with consumption which is controlled by the Con-Evator
bottom fl ap.
It is necessary only to make sure that material is continuosly available to the Con-Evator. An
alarm for missing material can be fi tted. (see Con-Evator manual).