Installation Instruction
NAKe Series Non-contact Level Switch Installation Instruction
SHANGHAI HUIBO AUTOMATIC GAUGE CO., LTD
Address: Room 1611, Lijing Yangguang Building, NO.19 Wuning Road,
Shanghai,China
Web Site:www.china-huibo.cn Email: huiboshanghai@163.com
6. Application of alarm cinder level under the water
IV. Level Switch Wiring
1. Preparation of wiring:
①、Rotate the Terminal Cover of the Level Switch counterclockwise,
while holding the cable lock.
②、 Unplug the power cable’s sheath about 50mm, Strip each core wire
and exposes the copper core about the 10mm.
Unplug the signal cable’s sheath about 50mm, Strip each core wire and
exposes the copper core about the 10mm.
③、Pass the cables through the cable lock, and label each core wire.
Level Switch
Angle iron
Dregs
Water
Dewatering
bin wall