Setup guide
Installing the ISS3124-RP2 NAS Server into a Rack
007-5922-001 13
Reliable Ground
A reliable ground must be maintained at all times. To ensure this, the rack itself should be
grounded. Particular attention should be given to power supply connections other than the direct
connections to the branch circuit (for example, the use of power strips, and so on).
Installing the ISS3124-RP2 NAS Server into a Rack
Use the following steps to install the ISS3124-RP2 NAS server rail kit in the rack.
See the information in “IS2224 JBOD Enclosure Cable Guide and Chassis Location” on page 23
to cable one or more IS2224 JBOD expansion units to the ISS3124-RP2 NAS server.
1. Attach the ISS3124-RP2 slide rails to the rack as shown in the example in Figure 2-2.
Figure 2-2 Attaching ISS3124-RP2 Rail Slides to the Rack
1
2
3