Setup guide
Installing the ISS3112-RP2 NAS Server into a Rack
007-5923-001 15
Circuit Overloading
Consideration should be given to the connection of the equipment to the power supply circuitry
and the effect that any possible overloading of circuits might have on overcurrent protection and
power supply wiring. Appropriate consideration of equipment nameplate ratings should be used
when addressing this concern.
Reliable Ground
A reliable ground must be maintained at all times. To ensure this, the rack itself should be
grounded. Particular attention should be given to power supply connections other than the direct
connections to the branch circuit (for example, the use of power strips, and so on).
Installing the ISS3112-RP2 NAS Server into a Rack
Use the following steps to install the ISS3112-RP2 NAS server rail kit in the rack.
See the information in “MIS NAS JBOD Cable Guide & Chassis Location” on page 39 for
information on cabling the ISS3112-RP2 NAS server to MIS JBOD expansion enclosures. See the
information in “IS2224 JBOD Enclosure Cable Guide and Chassis Location” on page 49 to cable
one or more IS2224 JBOD expansion units to the ISS3112-RP2 NAS server.