Specifications

SCPI Command Operation SG Series Programming
6-50 M550129-03 Rev G
OUTP:STAT ON
PROG:STAT RUN
The output of the supply for Example 3 should look like the following diagram:
Figure 6-3. Power Supply Output for Example 3
The above diagram shows how the new SEQ1 sequence looks when SEQ2 is installed as a
subsequence.
EXAMPLE 4
Issue *RST to establish a known state.
In this example, create a sequence that pauses at its end to let the last settings remain in
effect. To do this use the PAUSE command.
Now create a new SEQ3:
PROG:SEL:NAME “SEQ3”
PROG:MALL DEFAULT
PROG:DEF 1, VIMODE, 3, 4, 11, 10 //go to 3 volts, 4 amps, 11 volts ovp, for
10 sec
PROG:DEF 2, RAMPTOV, 3, 5, 4, 11, 10 //ramp from 3 volts to 5 volts in 10 sec
PROG:DEF 3, VIMODE, 5, 4, 11, 10 //hold 5 volts for 10 sec
PROG:DEF 4, RAMPTOV, 5, 3, 4, 11, 10 //ramp from 5 volts to 3 volts in 10 sec
PROG:DEF 5, VIMODE, 3, 4, 11, 10 //hold 3 volts for 10 sec
PROG:DEF 6, SUBCALL, “SEQ2” //call SEQ2 as a subsequence
PROG:DEF 7, VIMODE, 4, 5, 11, 6 //go to 4 volts, 5 amps, 11 volts ovp, for 6 sec
PROG:DEF 8, PAUSE //allow the output to remain at the last setting
3 volts for 10 sec
3 volts for 10 sec
5 volts for 10 sec
Ramp up to 5
volts in 10 sec
Ramp down to 3
volts in 10 sec
10 volts for 5 sec
Ramp down to 2
volts in 9 sec
4 volts for 6 sec