User's Manual

Table Of Contents
Model 1150A DVOR
Rev. - November, 2008
This document contains proprietary information and such information may not be disclosed
to others for any purposes without written permission from SELEX Sistemi Integrati Inc.
9-23
9.7.14.8
Setting Monitor 9960 Hz Dev High Limit
d. Select Monitors>>Configuration>>Alarm Limits. The Alarm and Prealarm limits will be displayed for
Monitor 1 and Monitor 2.
e. Enter the 9960 Hz Dev high alarm limit that is needed, then press [F7]. Monitor No. 1 and 2s new 9960
Hz Dev high limit will be entered into the station’s temporary memory.
f. Enter the 9960 Hz Dev high prealarm limit that is needed, then press [F7]. Monitor No. 1 and 2s new
9960 Hz Dev high prealarm limit will be entered into the station’s temporary memory.
9.7.14.9
Setting Monitor Field Intensity Low Limit
a. Select Monitors>>Configuration>>Alarm Limits. The Alarm and Prealarm limits will be displayed for
Monitor 1 and Monitor 2.
b. Enter the Field Intensity Low Alarm Limit that is needed, then press [F7]. Monitor No. 1 and 2’s new Field
Intensity Low Alarm Limit will be entered into the station’s temporary memory.
c. Enter the Field Intensity Low PreAlarm Limit that is needed, then press [F7]. Monitor No. 1 and 2s new
Field Intensity Low PreAlarm limit will be entered into the station’s temporary memory.
9.7.14.10
Setting Monitor Field Intensity High Limits
a. Select Monitors>>Configuration>>Alarm Limits. The Alarm and Prealarm limits will be displayed for
Monitor 1 and Monitor 2.
b. Enter the Field Intensity High Alarm Limit that is needed, then press [F7]. Monitor No. 1 and 2s new
Field Intensity High Alarm Limit will be entered into the station’s temporary memory.
c. Enter the Field Intensity High Alarm Limit that is needed, then press [F7]. Monitor No. 1 and 2s new
Field Intensity High PreAlarm Limit will be entered into the station’s temporary memory.
9.7.15
Records
a. Select RMS>>Config Backup and then press [enter]. This will place the new operating parameters into
electrically erasable memory.
b. A permanent copy should be placed onto the PMDT file system. Select System, Configuration Save. You
will be prompted for a file name. It is suggested that the configuration is saved into different files depicting
progress up through the commissioning with different file names for each.
9.8
INSTALLATION VERIFICATION TEST
a. Check to make sure that all RF and power connections have been accomplished.
b. If there are no further adjustments needed to be made to the antenna feed cables, fill the outside of the three
conduits with putty to seal against water and vermin.
c. Heat the shrink tubing on the 48 Sideband and 1 carrier antenna feed cables to provide a moisture seal on
the cable connections.
9.8.1
Special Tests
Perform verification procedures of Section 6.