Owner's manual

SEEDHAWK®AIRCARTOPERATOR’SMANUAL20
4.2.2 OPERATINGTHEAUGER
1. Ensure that all screens and shrouds are in
place and that the cleanout gate, on the
bottomofeachmeter,isclosed,Figure8.
2. Activate tractor hydraulic circuit #4, and
pull the diverter valve up to the auger
circuit.
3. Thehandleontheaugertubeisthecontrol
to operate the auger flighting in a forward
orreversedirection.
4. Whetherfillingorunloadingtheaircart,the
augerperformsatitshighestcapacitywhen
productisfallingdirectlyintotheflighting.
4.2.3 AUGERPOSITIONFORUNLOADINGAIRCART
1. Usingyourremote,allowtheaugertubeto
pivotunderanyoftheaircartcompartments
inordertoemptythem,Figure9.
2. Loosen the cross thumb‐nuts on the
cleanout gate, Figure 8, and slide it up to
allowproducttofallbetweentheairstream
tubes.
3.
Once emptied, the bottom airstream door
can be removed for complete cleanout
belowthemeter.
Figure8
Figure9