User`s guide
38  XR500/XR100 User’s Guide User Menu
  XR500/XR100 User’s Guide  39User Menu 
Setting Holiday ABC Schedules for S1, S2, S3, S4, 
OUT, and DOOR Schedules
Three  Holiday  schedules  are  available  for  each  shift  (S1,  S2,  S3, 
S4),  each  output  relay  (OUT),  each door  access relay  (DOOR), 
and  through  their  respective  menu  options.    This  allows  a  shift, 
output,  or  door  to  have  three  different  schedules  for  holidays.  
For example, Holiday  Schedule  A for those  holidays when the 
building stays closed, Holiday Schedule B for a day that only opens 
for a morning, etc.  Also, Holiday Schedules can be used to cross 
multiple days.  These schedules become active and supersede the 
current  day’s  schedule  when a  Holiday  Date occurs.    See  Setting 
Holiday Dates (HOL).
1.  After  you  have accessed  the  SCHEDULES?  menu  and  the 
schedule options, S1 S2  S3 S4,  display, press the COMMAND 
key until the display changes to SUN MON TUE WED.  Press 
the COMMAND key again to display THU FRI SAT HOL.
2.  Select HOL to program holiday schedules.
3.  The keypad displays HOL: A  B  C .  Select A to set the rst of 
three holiday schedules.
4.  The keypad displays A - : AM PM.
Note:  After  Selecting  the  schedule,  the  keypad  displays  any 
current times previously set for that holiday.  This feature allows 
you to review the programmed times.
5.  If times display, the keypad then displays DELETE     KEEP.  
Select DELETE to enter new times.
6.  The keypad then displays ON TIME? or OPENING TIME?.  This 
is followed by the display – : AM PM. 
  Enter a new time and select AM or PM. 
  The display changes to OFF TIME? or CLOSING TIME?.  This is 
followed by the display – : AM PM. 
  Enter a new time.
  Enter all schedule times using a 12 hour clock.  For example, 
to enter 6 AM you would enter 0 + 6 + 0 + 0 select AM.  For 
11 PM you would enter 1 + 1 + 0 + 0 and select PM. 
7.  The keypad returns to HOL: A B C  allowing you to enter a 
B and/or C holiday schedule for the same Shift (S1, S2, S3, 
or S4), Output or Door.  Go back to step 3 to add additional 
holiday schedules.