Specifications
Configuring Point Control Schedules
PlantScape Server and Client Configuration Guide 361
For status points:
• The target value for an OP parameter can be set to 0 or 1 for single-bit
output points and 0-3 for dual-bit output points.
• The MD parameter can be set to any value between 0 to 15 (where 0 is
manual, 1 is auto, and so on).
For more information about status point parameters, see “Status Point
Parameters” on page 123.
For flexible points, any writable numeric parameter can be controlled. You
need to know the numeric value for enumeration parameters (such as
Digital States or Nodes). For more information about flexible points, see
“Point Types” on page 118 and the documentation for the device.
Type
The type of schedule action:
Type Description
One-shot The control will be performed when the scheduled date and time becomes
equal to the current date and time, then deleted.
Daily The control will be performed when the scheduled date and time becomes
equal to the current date and time. It is then re-scheduled for the following
day at the same time.
Work day The control will be performed when the scheduled date and time becomes
equal to the current date and time, if that is between Monday and Friday
inclusive and the day has not been defined as a holiday. The control is then
re-scheduled for the following day at the same time to check for a work
day condition.
Weekend The control will be performed when the scheduled date and time becomes
equal to the current date and time, if that is a Saturday or a Sunday. The
control is then re-scheduled for the following day at the same time to
check for a weekend condition.
Holiday The control will be performed when the scheduled date and time becomes
equal to the current date and time if the day has been defined as a holiday
(see “Configuring Holiday and Shift Details” on page 359). The control is
then re-scheduled for the following day at the same time to check for a
holiday condition.
Monday
Tuesday
Wednesday
(and so on
through to)
Sunday
The control will be performed when the scheduled date and time become
equal to the current date time if it is the configured day of the week. The
control is then re-scheduled for the following day at the same time to
check for the specified day.