Specifications
16 – Configuring Schedules
360 R400
Configuring Point Control Schedules
To configure schedules, you need to be using a security level of SUPV or higher.
You configure schedules from the Point Control Schedule display.
To call up the Point Control Schedule display:
• Select Configure
⇒
Schedules
⇒
Point Control Schedules on the
System menu bar
• On the System Configuration Menu display, click Point Control Schedules.
This opens the Point Control Schedule display.
The Point Control Schedule display is divided into two sections. The top part of
the display shows a list of currently configured schedules. The Schedule
Maintenance fields at the bottom of the display are used for adding, deleting, or
updating schedules.
Each schedule displays the following fields:
Date
The date that the schedule will be performed.
Time
The time that the schedule will be performed.
Point ID
The point ID of the point that will be controlled by the schedule.
Parameter
The point parameter of the point that will be controlled by the schedule,
usually the OP (output).
For analog points, the SP, OP, MD, A1 - A4 parameters can be controlled.
For status points, the OP and MD parameters can be controlled.
You cannot schedule the control of a PV point parameter.
For flexible points, any writable numeric parameter can be controlled.
Target
The value that the point parameter will be controlled to.
For analog points:
• The target value of the SP and OP parameters can be set to any value
between the SP and OP control limits respectively.
• The MD parameter can be set to any value between 0 to 15 (where 0 is
manual, 1 is auto, and so on)
For more information about analog point parameters, see “Analog Point
Parameters” on page 126.
plscpcg.book Page 360 Monday, May 28, 2001 10:11 AM