User Manual

Sealer Sales Page 21
ST-1808-28 Tunnel Service Manual
TEMPERATURE CONTROL ADJUSTMENT
SEQUENCE OF OPERATION
3
4
5
1
2
A. Turn the START switch (1) to the on position to start the
machine. (Temperature will be displayed on temperature
control at this time. This will also start the cooling fan motor.)
B. Turn the HEATER switch (2) the on position, this will start
the blower, conveyor motors and heater.
C. Set the Conveyor Speed Control (3) to about mid-range
until the exact desired conveyor speed is determined later
(based on package size and sealer speed). Factory setting is 4.
D. Set the Temperature Controller (4) at the temperature you
believe will shrink your product. This temperature may need to
be adjusted higher or lower until you have achieved the shrink
you are happy with for that product. As long as you are