Owner`s manual
16 
SET(U)-F / ITT(U)-F Manual 
IM091221 
RD: FEB 2014 
RL: 8B 
FIGURE 9: COUPLER INSTALLATION (NOTE: See Section 9.3 for ‘Special Couplers’ at 
first tube joint: 100,000 x 20 ft & 175 / 200,000 models) 
1. Tube   
2.  Swaged end of upstream tube 
3. Tube Coupler     
4.  Centre coupler over tube joint 
Tighten coupler bolts to 40 ft-lbs. 
Note: Flange Gasket not required between burner and 
tube flange 
1.  Fifth Nut (Holds Inner Burner to Housing - Do Not 
Loosen or Remove) 
2.  Insert four burner bolts through the tube flange, 
secure tightly with lock nuts. 
3.  Secure suspension chain to eye bolt to stabilize 
burner 
FIGURE 8: BOLT BURNER TO TUBE FLANGE 
FIGURE 10: HANGER / REFLECTOR ORIENTATION HORIZONTAL TO 45
0
FOR ANGLE LESS 
THAN 45° USE 
CHAIN TO BOTH 
EYES ON HANGER 
45° 
45° 
4 
3 
1 
1 
2 
FIGURE 7: STRAIGHT TUBE TYPICAL HANGER & SUPPORT SPACINGS 
 8 - STEEL TUBE(S) 
 9 - REFLECTOR 
10 - FLUE VENT TERMINAL 
11 - BURNER SUPPORT CHAIN 
12 - HANGER SUPPORT 
CHAINS 
 4B - JS-0532-VC 4” WALL CAP 
 4C - JA-0528-XX 4” ROOF CAP 
5 - SIGHT GLASS 
6 - ALUMINIZED TUBE WITH 
FLANGE 
7 - TORCTITE TUBE COUPLER 
1 - END CAP 
2 - WIRE HANGER 
3 - BURNER ASSEMBLY   
4 - COMBUSTION AIR OPTIONS: 
 4A - JS-0532-SE 4” INTAKE 
ADAPTER 
SUSPEND ALL TUBES BY TWO (2) HANGERS PER 10’ LENGTH, LOCATE HANGERS BETWEEN 6” 
to 24” FROM EACH TUBE CONNECTION. 
1ST & 2ND TUBES FROM BURNER END: INSTALL WELDED SEAM FACING DOWNWARD.  
6” MIN. to 24” MAX. 