Installation Guide

2
Copyright © 2014 Schneider Electric. All Rights Reserved.
All trademarks are owned by Schneider Electric Industries SAS or its affiliated companies.
www.SEsolar.com
Conext Conduit Box Installation Guide
865-1025-01
E
Wiring the AC, DC, and Network Cable Connections
F
Secure the Front Panel of the Conduit Box
Re-attach the front panel of the Conduit Box when the wiring is complete
1. Slide the bottom lip of the front panel over the lower edge of the rear panel.
2. Align the two holes in the front panel with the two holes in the back panel.
3. Using two #10-16x3/8" tapping screws (provided), secure the front panel to the rear
panel as shown.
Route the AC, DC and Xanbus network wiring through the Conduit Box.
For detailed instructions and wiring diagrams, see the Conext XW+ Inverter/Charger
Installation Guide.
C
Knockout Dimensions
D
Wall Mounting the Conduit Box
Remove the Conduit Box front panel, the left or right sideplate and the
raceway knockout
Secure the Conduit Box to the Conext XW+
Either sideplate can be removed depending on the location of the adjacent PDP and
Conext XW+. If the Conduit Box is located between two XW+ units, then remove both
sideplates and knockouts.
Remove sideplate and
raceway knockout
IMPORTANT: Before installing the Conduit Box, wall mount the Conext XW+.
For detailed mounting instructions, see the Conext XW+ Inverter/Charger Installation Guide.
1
Wall mount the Conext XW+
Secure the Conduit Box to the wall
Using two screws suitable for the mounting surface (not provided), secure the bracket
at the bottom edge of the rear panel to the wall.
1. Align the keyhole slots on the top edge of
the Conduit Box with the corresponding
screws on the bottom of the inverter.
Loosen the screws if necessary.
2. Hang the Conduit Box on the XW+ unit by
fitting the keyholes to the screws and
pushing towards the wall until snug.
When removing your choice of knockouts, ensure no debris remains inside the chassis.
Insert appropriately-sized conduit bushings.
Wall Mounting Considerations
If conduit is routed from the floor, remove the bottom panel of the Conduit Box before
wiring. Remove the appropriate knockouts and re-attach the bottom panel once to
proceed with conduit installation and wiring.
If conduit is routed through the wall on which the XW+ unit and PDP are mounted,
remove the appropriate knockouts on the back panel of the Conduit Box.
Use plastic cable ties for cable management inside the Conduit Box.
EQUIPMENT DAMAGE
Do not drill, cut or punch holes into the Conduit Box, XW+ chassis, or Power Distribution
Panel. Use only the knockouts provided for conduit entry.
Failure to follow these instructions can result in damage to equipment.
NOTICE
Remove interior screw to
remove the left or right
sideplate
Side Knockouts
Back Knockouts
Bottom Knockouts
Inner: 3/4" Trade (PG 21)
Outer: 1" Trade
Inner: ISO-16
Outer: 1/2" Trade (PG 16)
Inner: ISO-40
Outer: ISO-50
Inner: 1 1/2" Trade
Outer: 2" Trade
Horizontal raceway
for routing Xanbus,
AC Sync, Aux, and
BTS cabling between
inverters or outside
the unit
V-raceway for routing
Xanbus, AC Sync,
Aux, and BTS cabling
to data ports on the
bottom of the inverter
Inner: 2" Trade (62.7 mm)
Outer: 2 1/2" Trade (75.6 mm)
Inner: (22.2 mm or PG21)
Outer: (28.2 mm)
Inner: 3/4" trade (28.2 mm or PG21)
Outer: 1" trade (35.0 mm)
Inner: 2" trade (62.7 mm)
Outer: 3" trade (90.0 mm)
Inner: 1/2" trade (22.2 mm or PG16)
Outer: 3/4" trade (28.0 mm)
Inner: 1/2" trade (22.2 mm or PG16)
Outer: 3/4" trade (28.0 mm)
Fits up to 8 mm wide cable ties
Secure the bracket with wall screws (not provided)