Documenting the Network Layout
890 USE 100 00
135
Trunk Cable and Taps
Summarize the amount of cable that will be required. Convert the
network cable length into standard reel lengths of 100, 500, or 1000 ft.
If cable will be ordered as two or more reels, specify reel lengths that
will allow you to run continuous cable segments between sites, without
splices. On dual-cable layouts, make sure that this requirement is met
for each cable run.
Summarize the amount of taps that will be required.
Drop Cables
Summarize the drop cables in each size that will be required.
Labels
Summarize the types and quantities of labels that will be required to
properly identify the network components for installation and future
servicing.
Installation Hardware
Enter the types and quantities of hardware items that will be required
to install, secure, and support the network cable and devices.
Tools/T est Equipment
Enter the types and quantities of tools and test equipment that will be
required to install and test the network.