Contents 1. General installation Guide 1. Introduction ···························································· 2. Product Outline ······················································· 3. DVM design process ················································ 4. Installation process & Guideline ·································· 5. Installation Procedure ··············································· 4 5 7 8 9 2. Preparation for installation 1.
4. Indoor Units installation 1. Ceiling Cassette Type (1WAY/2WAY/4WAY) ··················· 90 2. Duct Type (Slim/MSP) ············································ 96 3. Ceiling ······························································· 106 4. Console ····························································· 109 5. Wall-mounted Type ·············································· 111 5. Outdoor Units installation 1. Safety Information ·············································· 114 2.
1. General installation Guide 1. Introduction The following system diagram illustrates overall organization of the refrigerant pipes for installing a system air conditioner. Multiple outdoor units with sufficient capacities are installed in a location with good air ventilation for cooling and heating and a vibration-proof rubber mat is installed in the bottom of the outdoor unit to prevent vibration from being transferred to the building.
Installation guide 2. Product Outline 2-1. Outdoor Units Samsung provides you the perfectly optimized cooling and heating system with its latest and most innovative technology. World’s largest capacity will provide you the powerful performance all year long, no matter how hot or how cold. Furthermore, Samsung’s outdoor units barely make any noise or vibration during operations, and they are perfect for residential and commercial buildings, Always stay refreshed with Samsung system air conditioner.
1. General installation Guide 2-2. Indoor Units Samsung indoor units are not only equipped with high performing functions, but they are also beautifully designed to enlighten your space. Different types of indoor units will be more than enough to satisfy needs of your space and yourself. Only Samsung’s beautiful indoor units will provide you the conditioned air that you can enjoy.
Installation guide 3. DVM design process DVM is a multi-system air conditioner that changes its performance by different conditions such as design temperature, indoor and outdoor unit combination rates, heating operation rates, piping length, and level difference. It is important to select the appropriate design condition to the load specification of each room.
1. General installation Guide 4. Installation process & Guideline Striking a balance between System Installation & General Construction Work. . Note: 1. The division of the work should be thoroughly clarified. (This applies particularly to work relating to the connection of control wiring, fitting of remote controller and central control panel, boundary work on areas such as connection of drain piping and humidification supply piping, inspection and foundation) 2.
Installation guide 5. Installation Procedure 5-1. Procedure Note The above list indicates the order in which the individual work operations are normally carried out but this order may be varied according to the local conditions.
1. General installation Guide 5-2. Step by Step Installation Procedure 1) Refrigerant pipe construction (1) Familiarization with the diagram Process photo Work details Measure the actual construction diagram. Things to obey (installer) Familiarize with the construction diagram. Items to check (manager) Fully familiarize with the diagram to prevent problems while working on the site. (2) Straightening the refrigerant pipe Process photo Work details Straighten the refrigerant pipe.
Installation guide (5) Pipe cutting Process photo Work details Things to obey (installer) Items to check (manager) - Check if foreign substances are removed from the pipe. Cut the pipe. Prevent foreign substances from entering (If foreign substances are found, it can cause the pipe. performance degradation and malfunctions.) (6) Removing burr Process photo Work details Removing burr Things to obey (installer) Items to check (manager) - Remove burrs so that the cut side of the pipe is smooth.
1. General installation Guide (9) Anchor works Process photo Things to obey (installer) Work details Refer to the approved construction diagram when marking the indoor unit installation locations and make a hole for anchor installation. Items to check (manager) - Prevent scattering. Familiarize with the construction diagram. - Use a reel wire support. - Accurate location marking - Safeguard against falling accidents.
Installation guide (3) Brazing the branch pipes Process photo Things to obey (installer) Work details Brazing the branch pipe. - Nitrogen substituted brazing works on the branch pipe to prevent generation of foreign substance/oxide - Check for adequate pressure (0.01 to 2 0.1kg/cm ) Items to check (manager) Check the pressure and entry of nitrogen. 3) Refrigerant pipe works (air tightness works) (1) Entry of nitrogen Process photo Things to obey (installer) Work details Entry of nitrogen.
1. General installation Guide (4) Insulation of the branch pipe Process photo Things to obey (installer) Work details Heat-preserve the pipe if there is no nitrogen leakage. Check for leakages. Items to check (manager) Check for leakages. (5) Insulation of the branch pipe Process photo Things to obey (installer) Work details Heat preservation of the branch pipe Items to check (manager) Dense fill up to prevent Check the heat preservation missing heat preservation condition.
Installation guide (2) Mounting the drainpipe Process photo Things to obey (installer) Work details Fix the drainpipe in the channel or hanger. A group of two person should work on the pipe (not using excessive force). Items to check (manager) Check the channel/hanger fixing intervals (1.5m or less) (3) Checking the drain slope Process photo Things to obey (installer) Work details Checking the gradients. Obtain good slope to facilitate smooth drainage of the condensed water.
1. General installation Guide (6) Pipe work on the indoor unit side Process photo Things to obey (installer) Work details Pipe work on the indoor unit side. Obtain a slope (1/100) Items to check (manager) Check the slope. (7) Vent installation Work details Things to obey (installer) Install a vent to facilitate smooth drainage of water. Install one unit at the end of the equipment. Work details Things to obey (installer) Process photo Items to check (manager) Check vents installation.
Installation guide 5) Power communication works (1) Power cable pipe works Process photo Things to obey (installer) Work details Place a power cable pipe in the correct location. Use Standard quality materials. Items to check (manager) Check for bending of the pipe. (2) Inserting cables Work details Things to obey (installer) Items to check (manager) Insert the standard power communication cable in the pipe. Be careful not to damage the cable while inserting it. Check the cable condition.
1. General installation Guide (3) Connecting the equipment Process photo Things to obey (installer) Work details Mounting an indoor unit. A group of two works on the indoor unit. Items to check (manager) Check for levelness of the indoor unit and damage to the indoor unit. (4) Inserting a vibration-proof rubber mat Process photo Things to obey (installer) Work details Insert a vibration proof rubber mat between the bolt and the indoor unit to prevent transfers of the vibration.
Installation guide (7) Connecting the power communication cables Process photo Things to obey (installer) Work details Connect the power communication cable to the indoor unit. Use a ring terminal to make a connection. Items to check (manager) Check if the ring terminal is used. (8) Insulation works Process photo Things to obey (installer) Work details Pipe insulation works. Do not damage the insulation materials. Items to check (manager) Check the heat preservation and the slope.
1. General installation Guide (2) Conveying the outdoor unit Process photo Things to obey (installer) Items to check (manager) A group of four move the outdoor unit(22HP) Check for damages in the outdoor unit. Work details Checking the outdoor unit. (3) Mounting the vibration-proof board Process photo Things to obey (installer) Work details Mounting the vibration-proof board. Install it in the upper area. Items to check (manager) - Do not change the location of the vibrationproof board.
Installation guide (6) Connecting the outdoor unit’s pipes Process photo Things to obey (installer) Work details Connecting the outdoor unit’s pipe. Connect the pipe to the outdoor unit and perform heat preservation. Items to check (manager) Check the heat preservation of the outdoor unit. (7) Vacuum works Process photo Work details Things to obey (installer) Create vacuum inside the pipe.
1. General installation Guide (2) Refrigerant injection Process photo Things to obey (installer) Work details Refrigerant injection - Accurate refrigerant injection - Keep the Gas cylinder vertically downward during charging. Items to check (manager) Estimate the adequate amount of refrigerant. (3) Completed injection of refrigerant Process photo Things to obey (installer) Work details Completed injection of refrigerant Check if the amount of injection is accurate.
Installation guide (2) Panel installation Process photo Things to obey (installer) Work details - Do not apply excessive Panel installation force. - Use a clean glove. Items to check (manager) - Check if the exterior is dirty. - Check for damage. (3) Finish Process photo Things to obey (installer) Work details End Check the levelness and any blade damage. Items to check (manager) Check for twisting and test the entire unit.
1. General installation Guide (3) Connecting a interface module Process photo Work details Things to obey (installer) Connect a interface module to the outdoor unit. Assign an accurate interface module number. Items to check (manager) Check the interface module number. (4) Connecting a interface module to S-net Process photo Work details Things to obey (installer) Connecting the S-net program to the interface module. Make a correct cable connection.
2. Preparation for installation Installation guide 1. Checking the Installation Site Class Noise vibration Pre-check items Handling methods and rules Reference - Is the place affected by ※ Necessary to install a noises or vibration at all? soundproof wall to prevent - Is the outdoor unit close to noise transfer to houses. a residential area? -Use a gallery for soundproof wall - Is the bottom of the outdoor constructions.
2. Preparation for installation Class Gallery Upper discharge type Pre-check items - Is the gallery spec suggested? Handling methods and rules - Louver angle should be less than 20° - Opening rate of more than 80%. - Select a louver with a smooth cross section. (Do not use a rainwater prevention louver.) - Can you clear 500 mm(20inch) or more from the front of the outdoor unit and 300mm(12inch) or more from the rear? [Tray and interfering pipes included.
Installation guide Class Pre-check items -What is the finishing material for ceiling? Ceiling finishing - Is the ceiling sunken? Handling methods and rules Reference - If the ceiling is made of plaster boards, install an access hole depending on the internal height of the ceiling. -If the ceiling is made of ceiling tile, then no need to install an access hole.
2. Preparation for installation Class Drain Pre-check items - Is the discharge area free of bad odors? Installation - Is the location of the MCU, or location EEV proper? Handling methods and rules Reference ※ Do not join rainwater pipes and sewage water pipes. If unavoidable, then join them below the first floor to prevent reverse flows into the indoor unit. - ※ If installed near human residence such as living rooms or indoor, it can generate noise. ※ Do not install it in a fire fighting zone.
Installation guide 2. Product handling Problem analysis Dropping the product, due to rough or careless handling of the product during unloading process. Consequence It will cause the product damage/deformation and may also cause motor fixation kit to fall off. Such consequences will interrupt normal operation of the product and lead to noise generation. Furthermore, severe damages to the electrical parts may cause performance decrease and even serious accident which may involve personal injury.
2. Preparation for installation Problem analysis A chassis of outdoor unit is bent and a heat exchanger of the condenser is damaged due to inappropriate transportation method. Consequence When moving the product, you must lift up and down the product gently. When the product is scratched, product will corrode or get rust. If the heat exchanger of the condenser gets damaged, it will cause deteriorating performance and even make a leakage from the pipe.
Installation guide Problem analysis Product is left alone in the open site. If the ground gets wet with water after rain or due to other reasons, it will cause bad effect on the product. Consequence If the indoor unit products gets soaked, water will damage the packaging first and then it may get into the indoor unit and damage the electrical parts. Such damage may cause critical safety trouble. Standard procedure When leaving the product in the site, you must store them properly.
2. Preparation for installation Problem analysis Pile of indoor units in the site is too high and some of the products are even piled up vertically. Consequence Pile may fall down and cause personal injury. Indoor units lying on the bottom of the pile may get damaged due to pressure. Standard procedure Pile cannot be over 6rows and exceed 2m(6.5ft) in height. You cannot pile them vertically either. Proper method 1. Do not pile the indoor units too high.
Installation guide Problem analysis Indoor units are stored vertically. Not only that, it is left on the ground and the ground is wet with large amount of water. Consequence Pile may fall down and cause personal injury. Indoor units lying on the bottom of the pile may get damaged due to pressure. If the indoor units get soaked, water will damage the packaging first and then it may get into the indoor unit and damage the electrical parts Standard procedure Store the indoor units horizontally.
2. Preparation for installation Problem analysis Products are stored messily in the site and there is no manager in charge. Consequence Products are bumped into each other and pressed by one another which cause structural deformation. Internal parts of the product may get damaged or even lost. Standard procedure When storing the indoor unit : 1. Do not mix different models. 2. Do not leave them upside down. 3. Do not leave them vertically. 4. Do not tilt the indoor units. 5.
Installation guide Problem analysis Inappropriate product management caused outer packaging damage. Consequence After damage to the outer packaging of indoor unit, dust and other foreign substances entered to the product. Furthermore, you may lose , , drainpipe or other parts needed for installation. Standard procedure Strictly regulate the package removal before installing the indoor units. Manage and keep all the related parts and manuals thoroughly.
2. Preparation for installation Problem analysis Indoor unit installation is put on hold, and it was left with all the packaging removed. Dust, foreign substances, rain water, industrial water and dew got inside of the indoor unit. Because it was left with all the packaging removed while installation was put on hold. Consequence Dust and other foreign substances will get inside and cause pipe blockage or other malfunctions.
Installation guide Problem analysis Indoor unit, which is still in the middle of the installation process, is hanging on the ceiling without any protection. Consequence Indoor unit was hanging on the ceiling without any Protection which allows dust and other foreign substances to enter and cause malfunction.
2. Preparation for installation Problem analysis Safety net is not installed on 4-way cassette indoor unit. Consequence Safety of client and service agent can be at risk. Standard procedure Install the safety net for safety reasons. Proper method Make sure safety net is installed and let the customer know that they must not remove them for their own safety.
Installation guide 3. Materials and Tools Problem analysis R410a refrigerant system has relatively high pressure. If material does not meet the pressure-proof standards, then it may cause copper pipe explosion. Consequence Intensity and material specification doesn’t meet factory requirement and this could lead to explosion while using the product which could even bring personal injury.
2. Preparation for installation Problem analysis Layer of carbon, rust and dirty foreign substances were found on the outer surface of the copper pipe. Pipes must not have any scratches, indents or stains etc. Consequence Such defects decrease the strength of the pipe which may result in explosion, decrease in performance or leakage. Standard procedure You must select clean and dry copper pipe. Check inside of the pipe for any dust, water, indents or any signs of damage.
Installation guide Problem analysis Due to inappropriate protection management of the internal/external surface of the copper, large amount of oxidation, dust and foreign substances were seen. Consequence R410a refrigerant is very sensitively react with foreign substances : Mineral oil and compress oil will not solve with each other due to different chemical characteristics. Therefore, wax type materials may clog the hole of EEV or oil filters. Standard procedure Check if it is clean enough.
2. Preparation for installation Problem analysis After purchasing the pipe, it was not kept properly so dust, foreign substances, water and industrial water got inside of the pipe. Also pipe was left on the ground and people just walked on them. Consequence Water or foreign substances within the pipe will cause blockage that can lead to product malfunction or performance decrease.
Installation guide Problem analysis Thickness of the pipe does not meet the standards. Consequence Strength and the duration of the pipe will decrease which may cause breakup. Especially, R410a is a high pressure gas. Pipe with less thickness will have less strength, which may cause the pipe breakup. Standard procedure Required thickness – Soft type Outer diameter(mm) Min. Thickness(mm) Ø6.35 0.8 Ø9.52 0.8 Ø12.70 0.8 Ø15.88 1.0 Required thickness – Semi hard type Outer diameter(mm) Min.
2. Preparation for installation Problem analysis Selecting ø22.23 copper pipe, and 10mm insulation as shown in the picture. Consequence Low insulation effect cause large energy consumption and decrease in system performance. Condensation will easily form and leakage may occur when performing heating operation in regions with high temperature and humidity. Standard procedure Insulation material and quality must meet the minimum standard thickness requirements.
Installation guide Problem analysis Regular vacuum pump was used in vacuum operation. Consequence If the power of the vacuum pump cuts off unexpectedly then the oil gets back to the refrigerant system due to pressure difference. Standard procedure Use the vacuum pump which is 100% dedicated for R410a system with stop valve. Proper method Purchase and use the vacuum pump with the stop valve.
2. Preparation for installation Problem analysis R22 gauge was used in R410a system. Consequence If you use R22 gauge, remaining oil inside can generate wax type material which definitely badly affect POE oil of R410a system, possibly clogging refrigerant passage or causing compressor failure. Standard procedure Never utilize R22 gauge for R410a system to prevent the mineral oil from flowing in to the R410a system. Use the measuring instruments that meets the standard requirement.
3. Guideline for each installation process Installation guide 1. Sleeve work 1-1. Positioning of the pipe holes 1) The through holes for the drain piping should be positioned such that the pipes have a downward gradient. (The gradient must be at least 1/100. The thickness of the insulating materials must also be taken into consideration.) 2) The diameter of the through holes for the refrigerant piping should include allowance for the thickness of the heat insulation materials.
3. Guideline for each installation process ※ Selection of the refrigerant pipe sleeve’s diameter (a) Classification Liquid pipe diameter(mm) 6.35 9.52 Insulation (Based on 9t) 12.7 15.88 19.05 Insulation (Based on 13t) 22.22 32.35 24.35 77 27.52 80 38.7 91 41.88 94 45.05 97 48.22 101 9.52 47.52 92 95 106 109 113 116 12.7 50.7 95 98 109 113 116 119 15.88 53.88 98 101 113 116 119 122 19.05 57.05 101 105 116 119 122 125 22.22 60.22 105 108 119 122 125 128 25.
Installation guide 2. Insert work and support work 2-1.
3. Guideline for each installation process 2-2. Support work 1) Installation guideline for a vertical piping ▶ Down-stopper fixing guide Height Fixing interval Remarks 1 lower Fix a pipe every 5m(16.
Installation guide 3. Concealed Box work 3-1. Concealed Box work 1) Objectives - The concealed box aims at enhancing the interior inside the building by burying the drains, the copper pipes, the insulation materials, and the wires in the earlier phase, when you need to install an indoor unit 2) Functions (1) Buried in the wall on the pipe installation site and connecting the pipes, the drains and the wires. (2) Copper pipe protection, enhancing the exterior.
3. Guideline for each installation process 4. Refrigerant pipe construction 4-1. Drawing review 1) Compare the actual site with the drawing. When installing the refrigerant pipes, check interferences and the requirements for each pipe diameter size/length/quantity ahead of time. Temper grade and minimum thickness of the refrigerant pipe Cautions Outer diameter Minimum thickness 6.35 0.7 9.52 0.7 12.70 0.8 15.88 1.0 19.05 0.9 22.23 0.9 25.40 1.0 28.58 1.1 31.75 1.1 38.10 1.35 44.
Installation guide 2) Preparing a pipe (1) On the drawing, check the pipe diameter/length and the insulation material’s thickness and length. Prepare some margins for the dimension shown in the drawing (to give elastic tensions), Use a special cutter to cut the pipes. 3) Check the quantities of the branch pipe/header and the outdoor unit’s branch pipes.
3. Guideline for each installation process 4-2. Pipe Cutting 1) Burring - When performing burring works, point the pipe face downward to prevent entry of burr. 2) Taping – To prevent entry of moisture or dust, seal off the pipe completely.
Installation guide Covering is an extremely important operation as it prevents water, dirt or dust from getting inside the pipes. Moisture inside the pipes was a constant source of trouble in the past. The utmost care is required to nip this problem in the bud. The end of each pieces of pipe must be covered. “Pinching” is the most effective method but “taping” is an simple alternative which may be used according to the work area and term of work.
3. Guideline for each installation process 4-3. Insulating the Pipe, the Branch Pipe and the Header 1) Insulating the pipe (1) To block off external air, insulate the pipe with insulation material. (2) Insert the insulation material into the pipe and use a special EPDM glue to finish it.
Installation guide ① The thickness of the thermal insulation material must be determined in the light of the pipe sizes. Pipe size in. (mm) Thickness of insulation material Pipe size in(mm) Thickness of insulation material 1/4~1 (6.4mm~25.4mm) 1/2 or more (12.5mm or more) ② It will be necessary to increase the values in the above table for top floors or where conditions are hot and humid.
3. Guideline for each installation process (2) Selecting the insulation of the refrigerant pipe • Insulate the gas side and liquid side pipe referring to the thickness according to the pipe size. • The thickness according to the pipe size is calculated at the indoor temperature of 27°C and humidity of 80%. If installing in an unfavorable conditions from it, use thicker one. Pipe size (mm) Minimum thickness of insulation (mm) Remarks PE foam EPDM foam ø6.35~19.05 13 10 ø22.23~31.75 19 13 ø38.
Installation guide (4) Insulating the branch joint Y-joint & liquid side of the outdoor unit • Attach the insulation provided with a branch joint to the insulation purchased individually without a gap. Wrap the connected part with an insulation (purchased in the market) of a thickness of at least 10mm. • Use an insulation that should be able to handle the interior temperature over 120°C. Wrap the branch joint with an insulation of a thickness of at least 10mm.
3. Guideline for each installation process 4-4. Mounting the Pipe, the Branch Pipe and the Header 1) Mounting the insulated pipes. – The liquid/gas pipes should be made as a pair and the branch pipes require step differences with each other. 2) Install a hanger before and behind the branch pipe. - Install a hanger before and behind the branch pipe.
Installation guide 3) When installing the branch pipe, pay attention to the following cautionary items.
3. Guideline for each installation process Header joint ① Select the reducer fitted on the diameter of the pipe. ② Braze the pipes ends with caps if the number of connected indoor unit is fewer than header joint ports. < Liquid side > < Gas side > • When using A~J type of header joint, connect the header joint to the pipe with provided reducer. Cautions • When using K~Z type of header joint, connect the header joint to the pipe by cutting the provided reducer properly.
Installation guide 4) Installing the branch joints Outdoor joint Installation of outdoor joint Use the attached reducer properly according to the selected pipe size. Note • When using A~J type of Outdoor joint, connect the Outdoor joint to the pipe with provided reducer. • When using K~Z type of Outdoor joint, connect the Outdoor joint to the pipe by cutting provided reducer properly.
3. Guideline for each installation process 4-5. Connecting the Pipe/Branch Pipe 1) Reducer mounting - When connecting the pipes/branch pipes, you need a reducer to compensate for the diameter differences. The following specs are applied.
Installation guide 4-6. Installing the Branch Pipe for the Outdoor Unit 1) Connecting the outdoor unit pipe Heat Pump Working process Connection from front side Connection from bottom at the left/right side Working process • Separate the knock-out hole at the • First, remove the cover from unit. • Separate the knock-out hole to use. If bottom side of the unit and install the the hole is open, small animals such pipe.
3. Guideline for each installation process Heat Recovery Connection from front side Connection from bottom at the left/right side Single Installation Combination installation Caution for connecting the pipe Cautions • When connecting the pipe to the unit, the unit may get damaged by a brazing fire and a flame. Use a flame proofing cloth to protect the unit from a brazing fire or flame. Ambient air temperature sensor for detecting outside temperature is located on the left side of the welding part.
Installation guide 2) Piping works among outdoor units • The additional branch joints are needed for module installation of the outdoor units. • When outdoor units are installed in module, there is no designation of outdoor unit’s location according to capacity. • The connected piping should be positioned at the same or lower level with pipe cover hole. Cautions Correct piping work The refrigerant piping should be the same level or lower than connecting position of piping to outdoor units.
3. Guideline for each installation process 4-7. Brazing 1) Nitrogen substituted welding (1) Perform nitrogen substituted brazing works. Brazing the pipe • Make sure that there is no moisture inside the pipe. • Make sure that there are no foreign materials and impurities in the pipe. • Make sure that there is no leak. • Make sure to follow the instruction when brazing the pipe. The use of Nitrogen gas ① Use Nitrogen gas when brazing the pipes as shown in the picture.
Installation guide 2) Comparison with a case without nitrogen substitution With Nitrogen substitution Without Nitrogen substitution 3) Precautions for pipe-to-pipe brazing works Brazing work should be carried out either downwards or sideways. An upward direction should be avoided wherever possible(to prevent leakage.) CAUTION 1. Generally expending pipe brazing is performed with pan-coil type copper pipe, and socket blazing is performed with straight copper pipe. 2.
3. Guideline for each installation process 4-8. Nitrogen Pressurization Test 1) Leakage test Perform individual finishing of the liquid/gas pipe or connect the liquid/gas pipes for pinching and brazing. Air tightness test Nitrogen pressurization, 4MPa 2 No change in the gauge for 24 hours 41kgf/cm (4.1Mpa)pressure maintained Maintains 4Mpa for 24 hours. If no leakage, then pressure down to 1MPa. Maintain 1Mpa until connecting the outdoor/indoor units. Prevent corrosion in the copper pipes.
Installation guide 5. Refrigerant pipe flushing Flushing is a method of cleaning extraneous matter out of pipes using pressurized gas.
3. Guideline for each installation process (5) Check that the nitrogen is passing through the unit A liquid pipe. (6) Flushing. ① Block the end of the pipe with the insulation of your hand. ↓ ② When the gas pressure becomes too great to contain remove insulation quickly. (First flush) ↓ ③ Block the end of the pipe with insulation again.
Installation guide 6. Drainpipe Work 6-1. Diagram Review 1) On the diagram check the locations of the horizontal, branch and vertical pipes. (1) What is a horizontal pipe? It is a drainpipe where the drainpipes from the indoor unit are merged. (2) What is a branch pipe? It is a drainpipe from an indoor unit to a horizontal pipe.. (3) What is a vertical pipe? It is a vertical drainpipe that a horizontal pipe is connected for drain purpose.
3. Guideline for each installation process 2) On the diagram, check the location of the hanger for the drainpipe. (1) Due to the weight of the drainpipe and the condensed water, it can cause bending. The hangers should be separated by 1 to 1.5 meters. 3) Check the drainpipe diameter (horizontal, branch, vertical pipe) on the diagram. 4) Review installation of a horizontal pipe first. Install a branch pipe after installing an indoor unit. (Since the drainpipe location and direction could be changed.
Installation guide 6-2. Drainpipe Cutting and Insulation 1) Cut the drainpipe as its dimension and size are shown in the diagram. Use a specialized cutter for drainpipe 2) Use a special cutter for the PVC pipes. A PVC pipe cutter is shown in the following. (PVC pipe cutter photo) 3) Insulate the drainpipe that is cut. (Thickness of 5~10T, attach a photo of inserted insulation materials) Inserting the drainpipe insulation material (1) The drainpipe insulation materials should be non-flammable.
3. Guideline for each installation process 6-3. Mounting the Drainpipes 1) Mount a horizontal pipe in the hanger. Cutting and mounting the drainpipe 2) Perform 1/100 slope works on the horizontal pipe in the direction of the vertical pipe. (Discharge the condensed water.
Installation guide 6-4. Connecting the Drainpipe 1) At the area where the branch pipe is connected to the horizontal pipe, use a Tjoint to make connections between the horizontal pipe & branch pipe. 2) A T-joint should be faced upward. Precaution: T-joints should not be connected horizontally. 3) When you connect the horizontal pipe to the vertical pipe, do not make horizontal connections. Because the condensed water flowing from the upper area of the vertical pipe can back-flow into the horizontal pipe.
3. Guideline for each installation process 4) Branch pipe (indoor unit – horizontal pipe) construction method (1) Indoor unit with a drain pump ① The pipe coming from the indoor unit should have a trap to prevent reverse flows. ② The max height from the indoor unit’s drainpipe exit to the trap ranges from 300 to 550mm.
Installation guide (2) Indoor unit without a drain pump ① Form a reverse flow prevention P or U-trap on the pipe coming from the indoor unit. P-Trap, U-Trap pipe photo inserted here. ② An air-vent should be installed on the indoor unit side and located higher than the drainpipe height. ③ Or, install an air vent on the vertical pipe.
3. Guideline for each installation process 6-5. Drainpipe Combination and Bonding 1) Apply PVC glue to the joint area and wait for one to two minutes before combining them. 6-6. Drainpipe Water Soaking Test 1) Pour the water through the uppermost drainpipe or an air vent to check if the water flows smoothly. After that, for twenty-four hours, perform water soaking test to test leakages. In this test, the amount of water injection should be same as the amount of water discharge.
Installation guide 6-7. Insulation Material Finishing. 1) In a water soaking test, if there is no leakage, then insulate the bonded areas.
3. Guideline for each installation process 7. Insulation work 7-1. Purposes of Insulation and Piping (1) Explain the purposes. (2) List the pipes to be insulated. ① Refrigerant pipe ② Branch pipe ③ Drainpipe 7-2. Insulation Method (Procedure) ① Operational steps ① EPDM length should be longer then pipe length. Do not extend EPDM by force ② Put the pipe in EPDM insulation carefully so that the pipe will not get damaged with EPDM. ③ Apply bond on both side of cut surface.
Installation guide ③ ‘L’ Fitting connection part insulation All of the fitting connecting parts should be insulated. Bring face to face the each end of EPDM on fitting connection part. Make fitting cover to fit the EPDM insulation. Fitting cover should be overlapped with insulation min 1inch(2.5m). ① Insertion type: general insulation method ② Partitioning: Vertical insertion type ③ Elbow & edge area insulation methods 83 Bond the both cutting sides of fitting cover.
3. Guideline for each installation process 8. Gas leak test 8-1. Purposes 1) Leakage test step (1) 1st leakage test: After installing the pipe and the branch pipe, use Nitrogen at 4Mpa for testing. → Maintain 1Mpa. (2) 2nd leakage test: After connecting the pipe to the outdoor/indoor unit, use Nitrogen at 4Mpa for testing. 2) Detect leakages that can occur while connecting the pipe to the outdoor/indoor units. 3) 1st leakage test is completed, so now proceed with the 2nd leakage test.
Installation guide 8-2. Procedures (HR Module Installation Standard) 1) Before starting (1) Check if all the service valves are closed (liquid, gas, high pressure gas, Oil Equalizing pipes). (2) When using a nitrogen charging container, install pressure control regulator. (3) R410a gauge manifold – minimum 4 units, manifold hoses – five units or more. 2) The following pipes should pass a leakage test.
3. Guideline for each installation process 9. Vacuum drying 9-1. Purposes Using vacuum drying, the moisture inside the product or pipe can be evaporated. 9-2. Procedure (HR Modulation Installation Standard) 1) Before starting (1) Check if the second air tight test (outdoor unit, MCU, indoor unit pipes are all connected.). (2) After the second air tight test, check if the pressure is down to 1Mpa and check if there is any leakage of nitrogen gas.
Installation guide (1) Connect a hose to the liquid/gas/high pressure gas pipes and make the vacuum with a vacuum pump. (2) The equal oil pipe has gas type of refrigerants. Purge oxygen inside the equal oil pipe. (3) Compare the external temperature with the temperature below. Keep the vacuum until the gauge pressure reaches the value in the below table. (For more than 2-and–a-half hours) Boiling point Gauge pressure of water(℃) mmHg Pa Torr 40 -705 7333 55 30 -724 4800 36 26.
3. Guideline for each installation process 10. Charging Refrigerant 10-1. Purposes Add an additional amount of refrigerant for the installed pipe length to guarantee product performance and reliability. The additional amount of refrigerant varies depending on the product, the liquid pipe diameter and so on, so you must check the installation manual before proceeding. 10-2.
Installation guide (1) Connect a refrigerant box to the manifold gauge. (2) Since oxygen exists in the hose between the gauge manifold and the refrigerant box, open the refrigerant box valve to purge oxygen from the hose. (3) Place the refrigerant box on top of the electronic scale. (4) If it is a commercial product (sales with 11kg), then turn the refrigerant box upside down to place it on top of the electronic scale.
4. Indoor Units installation 1. Ceiling Cassette Type (1WAY/2WAY/4WAY) 1-1. Installation Standard - The installation location and direction of the indoor unit should be determined based on the relationship with various other processes such as the refrigerant pipe, the drainpipe and the power/communication cables and they should meet various requirements for other facilities (firefighting facilities etc.).
Installation guide (1) Firefighting detector 1.5m, Projection 2m separation required. 1.5m of separation Avoid installation in the direction of discharge (2) 4-way indoor unit height limited Installation within 3.5m ※ If the height limit is exceeded, the cooling/heating power can deteriorate. Use a long fall kit, install up to 5.2m.
4. Indoor Units installation (4) Y terminal construction for wireled remote controller installation. If constructed without a terminal, they are likely to make contact with the power cable and damage the PCB. (5) Indoor unit’s ring terminal construction Indoor unit’s terminal not used and Y terminal used Slipping out can lead to a short circuit fault.
Installation guide (7) Decoration panel installation (8) Drain installation ① The drainpipe should be installed within 100mm from the flexible hose, lift up from 100mm to 550mm and lift down 20mm or more. ② Install horizontal drainpipe with a slope of 1/100 or more and fix it by hanger space of 1~1.5m. ③ Install the air vent in the horizontal drainpipe to prevent water flow back to the indoor unit. - You may not need to install it if there were proper slope in the horizontal drainpipe.
4. Indoor Units installation ① Install main air vent at the front of the farthest indoor unit from the main drain when installed indoor units are more than 3. ② You may need to install individual air vent to prevent water flow back at the top of each indoor unit drainpipe. AIR-VENT interval of 10m~15m. Drainpipe hanger fixed within 1~1.5m. If the interval is more than 1~1.5m, bending of the PVC pipe can cause poor water drainage.
Installation guide 1-2. Installation Steps Sleeve work should be performed to make a space for passing pipe and wire through the wall or ground under construction. ① Place the pattern sheet on the ceiling at the spot where you want to install the indoor unit. Since the diagram is made of paper, it may shrink or stretch slightly due to temperature or humidity. For this reason, before drilling the holes maintain the correct dimensions between the markings.
4. Indoor Units installation 2. Duct Type (Slim/MSP) Type Slim Duct MSP Duct AVXDSH022/028/036/040/045 /056/071/090/112/140** AVXDUH056/071/090/ 112/128/140** Product Model 2-1. Installation Standard 2-2. Selecting the Installation (1) There must be no obstacles near the air inlet and outlet. (2) Install the indoor unit on a ceiling that can support its weight. (3) Maintain sufficient clearance around the indoor unit.
Installation guide 2-3. Space Requirements for Indoor Unit 1) If the ceiling is separable to single sheets like textile, then no need to install an inspection hole. 2) If the ceiling is not separable like plaster board: Depending on the distance between the product bottom and the ceiling top, install holes as follows.
4. Indoor Units installation 2-4. Indoor Units Installation 1) Place the pattern sheet on the ceiling at the spot where you want to install the indoor unit. 2) Insert bolt anchors, use existing ceiling supports or construct a suitable support as shown in figure. 3) Install the suspension bolts depending on the 3 the ceiling type. 4) Screw eight nuts to the suspension bolts making space for hanging the indoor unit. 5) Hang the indoor unit to the suspension bolts between two nuts.
Installation guide 10) Install drainpipe and drain hose. (1) Using a flexible hose clamp, fix the flexible hose.
4. Indoor Units installation (3)With the drain pump 11) Power and communication cable connection Indoor unit Indoor unit Indoor unit Use Y-type thimble for the Communication Connection (Outdoor to Indoor unit / Indoor to Indoor unit) & for Wired remote connection. Use Ring Type thimble for the power connection to the indoor unit.
Installation guide 2-5. Precaution with Duct type 1) The suction side should have at least the same cross sectional area as the discharge side. (1.
4. Indoor Units installation 2-6. Drain Pump Installation Process 1) Slim Duct (AVXDSH**)_Drain pump(MDP-E075S**1) (1) Please, Separate the cabinet of the indoor unite. Cabinet Base (2) Separate the cabinet base of the indoor unit and fix it with the drain pump. Ceiling Cabinet base (3) Connect the drain pump and the flexible hose pump. (4) Connect the flexible hose to the flexible hose pump.
Installation guide (5) Connect the float switch of the drain pump(Yellow) and power supply unit(Black) to the PCB of the indoor unit. (6) Adjust K4 DIP switch(SW03) to the "OFF" position. (7) Check water leakage of the drain hose port and the drainpipe after completing installation 2) Slim Duct (AVXDSH** 01)_ Drain pump(MDP-E075S**3) (1) Release the two screws on the control box and separate the cover and the cabinet side. (2) Remove the terminal and install the Drain Pump.
4. Indoor Units installation (5) Tie the drain pump wire and install the control box case. 3) MSP Duct (AVXDUH**)_ Drain pump(MDP-M075S***) (1) Remove the Control Cover (2) Remove the wire from PCB. Then remove the Control Box (3) Remove the part as seen in the picture. Assemble the Drain Kit and drain socket.
Installation guide (5) Insert the flexible hose into the drain socket until it clicks. (6) Connect the cable to the electrical component box as shown at the figure Adjust K4 DIP switch(SW05) to the “OFF” position.
4. Indoor Units installation 3. Ceiling 3-1. Space Requirements for Indoor Unit AVXTF** Type Under Ceiling Floor Standing 50mm Installation 50mm 300mm 300mm 3-2. Indoor Units Installation 1) Ceiling Installation (1) Select pipe directions. When the directions are selected, drill 4''(100mm, for pipe and cables) and 1-5/8'' (40mm, for drain hose) diameter holes on the wall (2) Drill holes for anchor bolts according to the distance and mount them. (3) Install the unit onto the ceiling.
Installation guide (4) If installing on dropped ceiling, install threaded rod onto anchor bolt-(expansion bolt) to long enough to suspend the unit right below the dropped ceiling and the install the unit suspending on the threaded rod. 2) Floor Installation (1) Select pipe directions. When the directions are selected, drill 4''(100mm, for pipe and cables) and 1-5/8'' (40mm, for drain hose) diameter holes on the wall (2) Install the hanging plate according to the distance and mount it.
4. Indoor Units installation 3) EEV Kits Installation (1) Check dimension and installation location. (2) Check installation place. (3) Connect the “IN” refrigerant pipe to the outdoor unit. (4) Connect the “OUT” refrigerant pipe to each indoor unit(A, B and C) (5) Insulate the connection piping. A joint part of pipe needs double thickness of insulation. (6)The EEV kit has to be installed that the user has no access to it.
Installation guide 4. Console 4-1. Space Requirements for Indoor Unit AVXTJ** 4-2. Indoor Units Installation (1) When you install the indoor with side-pipe connection, please make space more than 300mm from the wall (2) When you install the indoor at the inclined floor, please lean the set toward the drain hose and pipe connection to prevent water overflowing. (3) The body front should be opened to connect pipes Please release the 4 screws of body front and then pull it out from the bottom of the set.
4. Indoor Units installation (5) The pipes & cable should be gone through the bottom back hole. (6) Please remove 6 items when set is installed.
Installation guide 5. Wall-mounted Type 5-1.
4. Indoor Units installation Before fixing the installation plate to the wall or window frame, you must determine the position of the 3-1/8”(80mm) hole through which the cable, pipe and hose pass to connect the indoor unit to the outdoor unit.
Installation guide Connection of refrigerant piping & Insulation ① Insert bolt anchors, use existing ceiling supports or construct a suitable support. Ensure the ceiling is strong enough to support the weight of the indoor unit. Before hanging the unit, test the strength of each attached suspension bolt. ② Connect the “IN” refrigerant pipe to the outdoor unit. ③ Connect the “OUT” refrigerant pipe to each indoor unit(A, B and C). The liquid and gas pipes should not be crossed during piping connection.
5. Outdoor Units installation 1. Safety Information 1) Caution Signs (1) Make sure of a earthing. ① Do not connect the earth wire to the gas pipe, water pipe, lighting rod or telephone wire. If earthing is incomplete, electric shock or fire may occur. (2) Do not connect the heater to the outdoor unit and do not install altered duct as you please. ① The capacity may reduce, electric shock or fire may occur.
Installation guide (7) Install the outdoor unit within the angle of 25~55̊ depending on the building height as below table. Building height Protective angle Below 20m 55° Below 40m 35° Below 60m 25° Remarks 2. Preparing the Installation 1) Moving the Outdoor Unit (1) When moving with a crane or straps. ① Fasten the wire rope as seen in the picture. A. To protect damage or scratches, insert a piece of cloth between the outdoor unit and the wire rope. (2) When moving with a fork lift.
5. Outdoor Units installation 2) Detaching Fasteners ① Open the bottom cabinet with screw driver. ② Detach nut washer, washer and stopper nut from compressors with a tool. ③ Refasten the nut washer only.
Installation guide 3. Selecting Proper Location for Installation 1) Caution (1) Install the indoor unit away from any interfering sources such as radio, computer, stereo equipment and also select the place where the electrical wiring work can be possible. ① Especially keep the unit at least 3m away from the electrical equipment in an area electromagnetic waves generated and install the protection tube to protect the main power cable and communication cable.
5. Outdoor Units installation 4.
Installation guide 3) Recommended Case (1) At least 200mm(8inch) of space between the outdoor units is needed for service area and heat radiation. (2) When the product is installed in the site near the sea, wind-proof cover must be installed additionally, considering effects from typhoon and seasonal wind. Anti-corrosion type must be selected. (Special coating must be applied.) (3) All the ventilation systems, which are installed outdoors, should be apart from the outdoor unit.
5. Outdoor Units installation 5.
Installation guide 4) Anchor Specifications Size Diameter of drill bit(a) Anchor length(b) Sleeve length(c) Insert depth Fastening torque Φ10 14mm 75mm 40mm 50mm 30N·m 5) Caution (1) When tightening the anchor bolt. Tighten the rubber washer to prevent the outdoor unit bolt connection part from corroding. (2) When connecting the pipes. ① Check the strength of the roof to install the outdoor unit and make sure to have a waterproof floor of the roof.
5. Outdoor Units installation 6) Recommended Case (1) Construct a concrete foundation in accordance with the standards for the site where outdoor unit is being installed. ① H-beam: over 200mm ② Area of the concrete foundation must be 1.5 times larger than the outdoor unit. ③ Concrete foundation shouldn’t be slanted and condensed water needs to flow away without any stagnation (2) After placing the outdoor unit on the basic foundation, fix the outdoor unit with the anchor bolt(M12).
Installation guide 6. Drain Pipe Installation 1) Installing the Drainpipe (1) Insert the provided drain plug at the 2 sides of the bottom of the unit and then connect the drainpipe. (2) Install the drainpipe at the rear side of the unit to get a sufficient space for repairs and service. 2) When Installing Single Outdoor Unit 3) When Installing Multiple Outdoor Unit 4) Caution (1) Do not install a trap on the pipe. And, install the drainpipe horizontally with a slope of 1/50 or more.
5. Outdoor Units installation 7.
Installation guide 8. Installing the Outdoor Unit Harsh Environments 1) General Instructions (1) In abnormally harsh environments such as cold and/or windy areas, sufficient countermeasures to guard against excessive wind and snow should be taken to ensure the unit’s correct operation. (2) Snow-proof duct (field supply) should be fitted to the unit and direct exposure to the wind should be avoided as much as possible.
5.
Installation guide 9. Louver Installation 1) Requirements of Louver installation (1) Opening rate: 80% and more. (2) Louver angle(Blade Slope): 20° and less. (3) Louver shape: Don’t use drainable blade type. Good Bad (4) Air velocity of inlet side: 2.0m/s and less.
5. Outdoor Units installation 10. Electrical Wiring Work 1) General Instructions (1) All wiring, components and materials to be procured on the site must comply with the applicable local and national codes. (2) Be sure to comply with the specifications of the circuit breaker and power cable in installation manual.
Installation guide 3) Circuit Breaker Installation (1) 3 phase 4 wires ① Case 1 ② Case 2 (2) 3 phase 3 wires and 1 phase 2 wires ① Case 1 ② Case 2 129
5. Outdoor Units installation 4) Wiring Diagram (1) CO/HP Model (2) HR Model ※ If the communication cable between indoor and outdoor units and the communication cable among outdoor units are crossed, communication isn’t available.
Installation guide 5) Connecting the power terminal (1) Use solderless ring terminal to connect cable and terminal block. Good Bad (2) Install the cable according to a blueprint. (3) Install the wire box, with uncovered insulation tube, to the product. (4) During the installation in the site, make sure the wires and pipes do not contact each other because the vibration of compressor and high temperature pipe can make damage to wiring.
5. Outdoor Units installation 6) Power Cable Arrangement (1) Make sure all wiring should not contact with piping line during the field wiring work. If not, the vibration of compressor and high temperature pipe can make damage to wiring Good Bad 7) Circuit Breaker Installation (1) Install a circuit breaker. For safety and maintenance, we strongly recommend that MCCB and ELB and(or ELCB alone) have to be installed every outdoor unit.
Installation guide 11. Pump-Down Operation 1) General Instructions (1) Pump-down operation is to gather the refrigerant into outdoor unit. (2) If system is under extremely low pressure, compressor will be damaged. When low pressure go down 2kgf/㎠ or below, close the service valve quickly.
5. Outdoor Units installation 12. Pump-Out Procedure 1) General Instructions (1) Pump-out is the name of operation which pumps out the refrigerant from outdoor unit. (2) Pump out operation can be put into operation with more than 2 outdoor units installed. (3) If system is under extremely low pressure, compressor will be damaged. When low pressure go down 2kgf/㎠ or below, close the service valve quickly.
Installation guide 13. Setting the Option Switches & Function Keys 1) General Instruction (1) Refer to the installation manual for details. (2) Functions are activated by PCB of “Main unit” only.
5. Outdoor Units installation 14. Completing the Installation and Commissioning 1) Check List Contents Check Are the outdoor and indoor unit fixed securely? Is the place well-ventilated and ensures space for service? Is total number of connecting indoor units in the allowable range? Are the length and the difference between the refrigerant pipes within the allowable range? Is the ref.
Installation guide 137