Installation Guide

RUSTICAHARDWARE.com
6
3
03
2017
VERSION
MOUNTAIN MODERN Installation Instructions
TRACK INSTALLATION WITH HEADER
Figure 1
Center Line
for Track
Stud
Location
Figure 2
1-5/8”
1/2”
Panel/Door
Height
FIRST THINGS FIRST
Check to see if the sill or oor below the track area is level. If the sill or oor rises more than 1/2” the
panel or door may rub or not slide open completely. If the sill or oor is not level, measure from the
highest point of the sill or oor surface to the recommended track placement and adjust track placement
accordingly.
2. Using a level and a pencil, make a line above
the doorway the same length as the track.
1. To determine where the track should be
installed, rst measure the height of the door,
then add 2-1/8” to the door height. 1/2” will be
for the clearance between the bottom edge of
the door and the oor. 1-5/8” will be from the
top edge of the door to the center of the track.
(Figure 1).
HEADER INSTALLATION
NOTE:
e header should be 6” tall and 4” longer
than the track.
3. Using a stud nder, locate the studs along
the area the header will be installed. Mark
stud locations with a pencil (Figure 2).
TRACK PLACEMENT